The register lists Hiliana in Sufouh Gardens as complete, with a registered completion date of September 2014. Its last site inspection on record was in June 2016. The developer is Abyaar Real Estate Development (k.s.c) (Dubai Br).

100%

Built, at the site inspection of 12 June 2016

Construction complete

Registered completion date
September 2014
Construction started
January 2008
First registered
November 2008
Developer
Abyaar Real Estate Development (k.s.c) (Dubai Br)
Community
Sufouh Gardens
Units
179
Escrow bank
Dubai Islamic Bank
Name in Arabic
هيليانا
Project number
137
Site inspections
8

Schedule

The register lists Hiliana as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2009201120132015
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

12 June 2016

100%+12 pts

  • Hiliana construction site, inspection photo 1, 12 June 2016
  • Hiliana construction site, inspection photo 2, 12 June 2016
  • Hiliana construction site, inspection photo 3, 12 June 2016
  • Hiliana construction site, inspection photo 4, 12 June 2016

16 November 2015

88%+2.4 pts

  • Hiliana construction site, inspection photo 1, 16 November 2015
  • Hiliana construction site, inspection photo 2, 16 November 2015
  • Hiliana construction site, inspection photo 3, 16 November 2015
  • Hiliana construction site, inspection photo 4, 16 November 2015

13 August 2015

85%+13 pts

  • Hiliana construction site, inspection photo 1, 13 August 2015
  • Hiliana construction site, inspection photo 2, 13 August 2015
  • Hiliana construction site, inspection photo 3, 13 August 2015
  • Hiliana construction site, inspection photo 4, 13 August 2015

16 December 2014

72%+21 pts

  • Hiliana construction site, inspection photo 1, 16 December 2014
  • Hiliana construction site, inspection photo 2, 16 December 2014
  • Hiliana construction site, inspection photo 3, 16 December 2014
  • Hiliana construction site, inspection photo 4, 16 December 2014

16 April 2014

51%+5.4 pts

  • Hiliana construction site, inspection photo 1, 16 April 2014
  • Hiliana construction site, inspection photo 2, 16 April 2014
  • Hiliana construction site, inspection photo 3, 16 April 2014
  • Hiliana construction site, inspection photo 4, 16 April 2014

8 January 2014

45%+10 pts

  • Hiliana construction site, inspection photo 1, 8 January 2014
  • Hiliana construction site, inspection photo 2, 8 January 2014
  • Hiliana construction site, inspection photo 3, 8 January 2014
  • Hiliana construction site, inspection photo 4, 8 January 2014

22 May 2013

35%+16 pts

  • Hiliana construction site, inspection photo 1, 22 May 2013
  • Hiliana construction site, inspection photo 2, 22 May 2013
  • Hiliana construction site, inspection photo 3, 22 May 2013
  • Hiliana construction site, inspection photo 4, 22 May 2013

18 December 2012

20%

  • Hiliana construction site, inspection photo 1, 18 December 2012
  • Hiliana construction site, inspection photo 2, 18 December 2012
  • Hiliana construction site, inspection photo 3, 18 December 2012

All 67 site photos, by inspection date

Context

Own a unit in Hiliana?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Hiliana handover date?
Construction of Hiliana is recorded as complete, with a registered completion date of September 2014. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Hiliana?
Hiliana was 100% built at the site inspection on 12 June 2016. The site has been inspected 8 times since December 2012. The Land Department took 67 site photos at its inspections.
Is Hiliana delayed?
The register lists construction as complete.
Who is building Hiliana?
The registered developer is Abyaar Real Estate Development (k.s.c) (Dubai Br).
Which bank holds the escrow account for Hiliana?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.