Biltmore Sufouh construction progress
Biltmore Sufouh in Sufouh Gardens was registered to complete in January 2026 and is still under construction. At the last site inspection, in August 2026, it was 88% built. The developer is G J R E Real Estate.
90%
Built, at the site inspection of 20 August 2026
10 months past its registered completion date
- Registered completion date
- January 2026
- Finish at recent pace
- August 2027
- Construction started
- June 2022
- First registered
- May 2023
- Developer
- G J R E Real Estate
- Community
- Sufouh Gardens
- Units
- 477
- Escrow bank
- Emirates Islamic Bank
- Name in Arabic
- بلتمور صفوح
- Project number
- 2619
- Site inspections
- 11
Schedule
Biltmore Sufouh was registered to complete in January 2026, 10 months ago, and is still under construction. Over the last year of inspections it has added about 1.0 points a month. Kept at that rate, the site would reach 100% around August 2027.
Site inspections
20 August 2026
88%+2.3 pts
27 April 2026
85%+4.0 pts
30 December 2025
81%+5.1 pts
11 September 2025
76%+8.9 pts
13 May 2025
67%+6.1 pts
16 January 2025
61%+7.6 pts
26 September 2024
54%+3.0 pts
14 August 2024
51%+8.8 pts
11 March 2024
42%+6.5 pts
28 August 2023
35%+0.3 pts
Context
Own a unit in Biltmore Sufouh?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Biltmore Sufouh handover date?
- The registered completion date was January 2026, and the register still lists Biltmore Sufouh as under construction. At the pace of its recent inspections the site would reach 100% around August 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Biltmore Sufouh?
- Biltmore Sufouh was 90% built at the site inspection on 20 August 2026. The site has been inspected 11 times since April 2023. The Land Department took 109 site photos at its inspections.
- Is Biltmore Sufouh delayed?
- Yes. Its registered completion date of January 2026 has passed and the project is still listed as under construction.
- Who is building Biltmore Sufouh?
- The registered developer is G J R E Real Estate.
- Which bank holds the escrow account for Biltmore Sufouh?
- Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)







.jpeg&w=3840&q=75)
























.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)