The Terraces construction progress

The register lists The Terraces in Sobha Hartland as complete, with a registered completion date of February 2022. Its last site inspection on record was in November 2022. The developer is Bolton Real Estate Development.

100%

Built, at the site inspection of 17 November 2022

Construction complete

Registered completion date
February 2022
Construction started
November 2017
First registered
January 2018
Developer
Bolton Real Estate Development
Units
251
Escrow bank
Emirates NBD
Name in Arabic
ذا تيراسز
Project number
2013
Site inspections
10

Schedule

The register lists The Terraces as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%20182019202020212022
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

17 November 2022

100%+5.0 pts

  • The Terraces construction site, inspection photo 1, 17 November 2022
  • The Terraces construction site, inspection photo 2, 17 November 2022
  • The Terraces construction site, inspection photo 3, 17 November 2022
  • The Terraces construction site, inspection photo 4, 17 November 2022

18 January 2022

95%+8.6 pts

  • The Terraces construction site, inspection photo 1, 18 January 2022
  • The Terraces construction site, inspection photo 2, 18 January 2022
  • The Terraces construction site, inspection photo 3, 18 January 2022
  • The Terraces construction site, inspection photo 4, 18 January 2022

27 June 2021

86%+6.4 pts

  • The Terraces construction site, inspection photo 1, 27 June 2021
  • The Terraces construction site, inspection photo 2, 27 June 2021
  • The Terraces construction site, inspection photo 3, 27 June 2021
  • The Terraces construction site, inspection photo 4, 27 June 2021

14 February 2021

80%+7.8 pts

  • The Terraces construction site, inspection photo 1, 14 February 2021
  • The Terraces construction site, inspection photo 2, 14 February 2021
  • The Terraces construction site, inspection photo 3, 14 February 2021
  • The Terraces construction site, inspection photo 4, 14 February 2021

29 November 2020

72%+6.7 pts

  • The Terraces construction site, inspection photo 1, 29 November 2020
  • The Terraces construction site, inspection photo 2, 29 November 2020
  • The Terraces construction site, inspection photo 3, 29 November 2020
  • The Terraces construction site, inspection photo 4, 29 November 2020

25 August 2020

66%+15 pts

  • The Terraces construction site, inspection photo 1, 25 August 2020
  • The Terraces construction site, inspection photo 2, 25 August 2020
  • The Terraces construction site, inspection photo 3, 25 August 2020
  • The Terraces construction site, inspection photo 4, 25 August 2020

11 March 2020

51%+21 pts

  • The Terraces construction site, inspection photo 1, 11 March 2020
  • The Terraces construction site, inspection photo 2, 11 March 2020
  • The Terraces construction site, inspection photo 3, 11 March 2020
  • The Terraces construction site, inspection photo 4, 11 March 2020

7 November 2019

30%+10 pts

  • The Terraces construction site, inspection photo 1, 7 November 2019
  • The Terraces construction site, inspection photo 2, 7 November 2019
  • The Terraces construction site, inspection photo 3, 7 November 2019
  • The Terraces construction site, inspection photo 4, 7 November 2019

24 July 2019

20%+14 pts

  • The Terraces construction site, inspection photo 1, 24 July 2019
  • The Terraces construction site, inspection photo 2, 24 July 2019
  • The Terraces construction site, inspection photo 3, 24 July 2019
  • The Terraces construction site, inspection photo 4, 24 July 2019

13 August 2018

6.3%

  • The Terraces construction site, inspection photo 1, 13 August 2018
  • The Terraces construction site, inspection photo 2, 13 August 2018
  • The Terraces construction site, inspection photo 3, 13 August 2018
  • The Terraces construction site, inspection photo 4, 13 August 2018

All 102 site photos, by inspection date

Context

Sobha Hartland has 3 projects under construction, 82% built on average.

Own a unit in The Terraces?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the The Terraces handover date?
Construction of The Terraces is recorded as complete, with a registered completion date of February 2022. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on The Terraces?
The Terraces was 100% built at the site inspection on 17 November 2022. The site has been inspected 10 times since August 2018. The Land Department took 102 site photos at its inspections.
Is The Terraces delayed?
The register lists construction as complete.
Who is building The Terraces?
The registered developer is Bolton Real Estate Development.
Which bank holds the escrow account for The Terraces?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.