Casa Serene construction photos

21 photos taken by Dubai Land Department engineers at 3 site inspections, newest first. The percentage is how much of Casa Serene was built on the day of each visit.

13 July 202674% built

30 January 202552% built

28 February 202415% built

Back to Casa Serene construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.