42 East Residences construction progress

42 East Residences in Palm Deira is 2.5% built at the Land Department inspection of June 2026. Developer Gramercy Real Estate Development. Completion registered for April 2028.

2.5%

Built, at the Land Department site inspection of 16 June 2026

Running behind its date

Completion date (Land Department)
April 2028
Finish at recent pace
December 2054
Construction started
September 2025
Registered with the Land Department
October 2025
Developer
Gramercy Real Estate Development
Community
Palm Deira
Units
42
Escrow bank
Ajman Bank
Name in Arabic
إيست ريزيدنسز 42
Land Department project number
4094
Land Department site inspections
3

Schedule

Between September 2025 and June 2026 the site added about 0.3 points a month. At that rate it would finish around December 2054, more than three months after the April 2028 date registered with the Land Department.

0%25%50%75%100%202620272028
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

16 June 2026

2.5%+1.3 pts

  • 42 East Residences construction site, Land Department inspection photo 1, 16 June 2026
  • 42 East Residences construction site, Land Department inspection photo 2, 16 June 2026
  • 42 East Residences construction site, Land Department inspection photo 3, 16 June 2026
  • 42 East Residences construction site, Land Department inspection photo 4, 16 June 2026

3 March 2026

1.2%+1.2 pts

  • 42 East Residences construction site, Land Department inspection photo 1, 3 March 2026
  • 42 East Residences construction site, Land Department inspection photo 2, 3 March 2026
  • 42 East Residences construction site, Land Department inspection photo 3, 3 March 2026
  • 42 East Residences construction site, Land Department inspection photo 4, 3 March 2026

18 September 2025

0%

  • 42 East Residences construction site, Land Department inspection photo 1, 18 September 2025
  • 42 East Residences construction site, Land Department inspection photo 2, 18 September 2025

All 10 site photos, by inspection date

Context

Palm Deira has 95 projects under construction, 22% built on average.

Own a unit in 42 East Residences?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will 42 East Residences be completed?
The completion date registered with the Dubai Land Department is April 2028. At the pace of its recent inspections the site would reach 100% around December 2054. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of 42 East Residences is built?
2.5%, measured at the Land Department site inspection on 16 June 2026. The Land Department engineers have inspected the site 3 times since September 2025.
Is 42 East Residences delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of April 2028.
Who is building 42 East Residences?
The registered developer is Gramercy Real Estate Development.
Which bank holds the escrow account for 42 East Residences?
Ajman Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.