Queen'S Garden construction progress

Queen'S Garden in Nad Al Sheba Gardens is 42% built at the Land Department inspection of April 2026. Developer H M K Real Estate Development. Completion registered for August 2026.

42%

Built, at the Land Department site inspection of 23 April 2026

2 months past its registered completion date

Completion date (Land Department)
August 2026
Finish at recent pace
December 2029
Construction started
July 2024
Registered with the Land Department
October 2025
Developer
H M K Real Estate Development
Units
77
Escrow bank
Emirates Islamic Bank
Name in Arabic
كوينز غاردن
Land Department project number
4068
Land Department site inspections
2

Schedule

Queen'S Garden was registered to complete in August 2026, 2 months ago, and is still under construction. Over the last year of inspections it has added about 1.3 points a month. Kept at that rate, the site would reach 100% around December 2029.

0%25%50%75%100%20252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

23 April 2026

42%+8.6 pts

  • Queen'S Garden construction site, Land Department inspection photo 1, 23 April 2026
  • Queen'S Garden construction site, Land Department inspection photo 2, 23 April 2026
  • Queen'S Garden construction site, Land Department inspection photo 3, 23 April 2026
  • Queen'S Garden construction site, Land Department inspection photo 4, 23 April 2026

8 October 2025

34%

  • Queen'S Garden construction site, Land Department inspection photo 1, 8 October 2025
  • Queen'S Garden construction site, Land Department inspection photo 2, 8 October 2025
  • Queen'S Garden construction site, Land Department inspection photo 3, 8 October 2025
  • Queen'S Garden construction site, Land Department inspection photo 4, 8 October 2025

All 14 site photos, by inspection date

Context

Nad Al Sheba Gardens has 9 projects under construction, 52% built on average.

Own a unit in Queen'S Garden?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Queen'S Garden be completed?
The completion date registered with the Dubai Land Department is August 2026. At the pace of its recent inspections the site would reach 100% around December 2029. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Queen'S Garden is built?
42%, measured at the Land Department site inspection on 23 April 2026. The Land Department engineers have inspected the site 2 times since October 2025.
Is Queen'S Garden delayed?
Yes. Its registered completion date of August 2026 has passed and the Land Department still lists it as under construction.
Who is building Queen'S Garden?
The registered developer is H M K Real Estate Development.
Which bank holds the escrow account for Queen'S Garden?
Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.