Queen'S Garden construction progress
Queen'S Garden in Nad Al Sheba Gardens is 42% built at the Land Department inspection of April 2026. Developer H M K Real Estate Development. Completion registered for August 2026.
42%
Built, at the Land Department site inspection of 23 April 2026
2 months past its registered completion date
- Completion date (Land Department)
- August 2026
- Finish at recent pace
- December 2029
- Construction started
- July 2024
- Registered with the Land Department
- October 2025
- Developer
- H M K Real Estate Development
- Community
- Nad Al Sheba Gardens
- Units
- 77
- Escrow bank
- Emirates Islamic Bank
- Name in Arabic
- كوينز غاردن
- Land Department project number
- 4068
- Land Department site inspections
- 2
Schedule
Queen'S Garden was registered to complete in August 2026, 2 months ago, and is still under construction. Over the last year of inspections it has added about 1.3 points a month. Kept at that rate, the site would reach 100% around December 2029.
Site inspections
23 April 2026
42%+8.6 pts
8 October 2025
34%
Context
Nad Al Sheba Gardens has 9 projects under construction, 52% built on average.
Own a unit in Queen'S Garden?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Queen'S Garden be completed?
- The completion date registered with the Dubai Land Department is August 2026. At the pace of its recent inspections the site would reach 100% around December 2029. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Queen'S Garden is built?
- 42%, measured at the Land Department site inspection on 23 April 2026. The Land Department engineers have inspected the site 2 times since October 2025.
- Is Queen'S Garden delayed?
- Yes. Its registered completion date of August 2026 has passed and the Land Department still lists it as under construction.
- Who is building Queen'S Garden?
- The registered developer is H M K Real Estate Development.
- Which bank holds the escrow account for Queen'S Garden?
- Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Nad Al Sheba Gardens Phase 3Nearby in Nad Al Sheba Gardens. 97%, Due April 2026, passed.
- Nad Al Sheba Gardens Phase 4Nearby in Nad Al Sheba Gardens. 57%.
- Nad Al Sheba Gardens Phase 5Nearby in Nad Al Sheba Gardens. 38%.
- Nad Al Sheba Gardens Phase 6Nearby in Nad Al Sheba Gardens. 14%.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.