107 photos from 13 site inspections, newest first. The percentage is how much of Arabella 2 - Townhouses At Mudon was built on the day of each visit.

14 May 2020100% built

15 March 202097% built

12 March 202096% built

26 September 201987% built

3 September 201985% built

11 April 201967% built

27 January 201957% built

19 September 201841% built

18 April 201827% built

21 November 201714% built

14 June 20177.7% built

9 February 20173.5% built

5 October 20160.8% built

Back to Arabella 2 - Townhouses At Mudon construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.