Arabella 2 - Townhouses At Mudon construction progress

The register lists Arabella 2 - Townhouses At Mudon in Mudon as complete, with a registered completion date of May 2020. Its last site inspection on record was in May 2020. The developer is Mdn Real Estate.

100%

Built, at the site inspection of 14 May 2020

Construction complete

Registered completion date
May 2020
Construction started
January 2016
First registered
January 2016
Developer
Mdn Real Estate
Community
Mudon
Units
496
Escrow bank
Emirates NBD
Name in Arabic
أرابيلا 2 - تاون هاوسز في مدن
Project number
1714
Site inspections
13

Schedule

The register lists Arabella 2 - Townhouses At Mudon as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2017201820192020
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

14 May 2020

100%+3.5 pts

  • Arabella 2 - Townhouses At Mudon construction site, inspection photo 1, 14 May 2020
  • Arabella 2 - Townhouses At Mudon construction site, inspection photo 2, 14 May 2020
  • Arabella 2 - Townhouses At Mudon construction site, inspection photo 3, 14 May 2020
  • Arabella 2 - Townhouses At Mudon construction site, inspection photo 4, 14 May 2020

15 March 2020

97%+0.5 pts

  • Arabella 2 - Townhouses At Mudon construction site, inspection photo 1, 15 March 2020
  • Arabella 2 - Townhouses At Mudon construction site, inspection photo 2, 15 March 2020
  • Arabella 2 - Townhouses At Mudon construction site, inspection photo 3, 15 March 2020
  • Arabella 2 - Townhouses At Mudon construction site, inspection photo 4, 15 March 2020

12 March 2020

96%+8.8 pts

  • Arabella 2 - Townhouses At Mudon construction site, inspection photo 1, 12 March 2020
  • Arabella 2 - Townhouses At Mudon construction site, inspection photo 2, 12 March 2020
  • Arabella 2 - Townhouses At Mudon construction site, inspection photo 3, 12 March 2020
  • Arabella 2 - Townhouses At Mudon construction site, inspection photo 4, 12 March 2020

26 September 2019

87%+2.0 pts

  • Arabella 2 - Townhouses At Mudon construction site, inspection photo 1, 26 September 2019
  • Arabella 2 - Townhouses At Mudon construction site, inspection photo 2, 26 September 2019
  • Arabella 2 - Townhouses At Mudon construction site, inspection photo 3, 26 September 2019
  • Arabella 2 - Townhouses At Mudon construction site, inspection photo 4, 26 September 2019

3 September 2019

85%+19 pts

  • Arabella 2 - Townhouses At Mudon construction site, inspection photo 1, 3 September 2019
  • Arabella 2 - Townhouses At Mudon construction site, inspection photo 2, 3 September 2019
  • Arabella 2 - Townhouses At Mudon construction site, inspection photo 3, 3 September 2019
  • Arabella 2 - Townhouses At Mudon construction site, inspection photo 4, 3 September 2019

11 April 2019

67%+9.5 pts

  • Arabella 2 - Townhouses At Mudon construction site, inspection photo 1, 11 April 2019
  • Arabella 2 - Townhouses At Mudon construction site, inspection photo 2, 11 April 2019
  • Arabella 2 - Townhouses At Mudon construction site, inspection photo 3, 11 April 2019
  • Arabella 2 - Townhouses At Mudon construction site, inspection photo 4, 11 April 2019

27 January 2019

57%+16 pts

  • Arabella 2 - Townhouses At Mudon construction site, inspection photo 1, 27 January 2019
  • Arabella 2 - Townhouses At Mudon construction site, inspection photo 2, 27 January 2019
  • Arabella 2 - Townhouses At Mudon construction site, inspection photo 3, 27 January 2019
  • Arabella 2 - Townhouses At Mudon construction site, inspection photo 4, 27 January 2019

19 September 2018

41%+14 pts

  • Arabella 2 - Townhouses At Mudon construction site, inspection photo 1, 19 September 2018
  • Arabella 2 - Townhouses At Mudon construction site, inspection photo 2, 19 September 2018
  • Arabella 2 - Townhouses At Mudon construction site, inspection photo 3, 19 September 2018
  • Arabella 2 - Townhouses At Mudon construction site, inspection photo 4, 19 September 2018

18 April 2018

27%+12 pts

  • Arabella 2 - Townhouses At Mudon construction site, inspection photo 1, 18 April 2018
  • Arabella 2 - Townhouses At Mudon construction site, inspection photo 2, 18 April 2018
  • Arabella 2 - Townhouses At Mudon construction site, inspection photo 3, 18 April 2018
  • Arabella 2 - Townhouses At Mudon construction site, inspection photo 4, 18 April 2018

21 November 2017

14%+6.8 pts

  • Arabella 2 - Townhouses At Mudon construction site, inspection photo 1, 21 November 2017
  • Arabella 2 - Townhouses At Mudon construction site, inspection photo 2, 21 November 2017
  • Arabella 2 - Townhouses At Mudon construction site, inspection photo 3, 21 November 2017
  • Arabella 2 - Townhouses At Mudon construction site, inspection photo 4, 21 November 2017

All 107 site photos, by inspection date

Own a unit in Arabella 2 - Townhouses At Mudon?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Arabella 2 - Townhouses At Mudon handover date?
Construction of Arabella 2 - Townhouses At Mudon is recorded as complete, with a registered completion date of May 2020. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Arabella 2 - Townhouses At Mudon?
Arabella 2 - Townhouses At Mudon was 100% built at the site inspection on 14 May 2020. The site has been inspected 13 times since October 2016. The Land Department took 107 site photos at its inspections.
Is Arabella 2 - Townhouses At Mudon delayed?
The register lists construction as complete.
Who is building Arabella 2 - Townhouses At Mudon?
The registered developer is Mdn Real Estate.
Which bank holds the escrow account for Arabella 2 - Townhouses At Mudon?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.