Naya At District One construction photos
42 photos taken by Dubai Land Department engineers at 8 site inspections, newest first. The percentage is how much of Naya At District One was built on the day of each visit.
22 July 202656% built
28 April 202637% built
6 January 202626% built
23 September 20256.8% built
11 June 20252.3% built
19 March 20250.2% built
18 December 20240% built
29 May 20230% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.