Skip to content

Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 3 construction progress

The register lists Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 3 in Mohammed Bin Rashid Al Maktoum City -District -1 Community as complete, with a registered completion date of January 2022. Its last site inspection on record was in February 2022. The developer is District One.

100%

Built, at the site inspection of 16 February 2022

Construction complete

Registered completion date
January 2022
Construction started
December 2017
First registered
November 2017
Developer
District One
Community
Mohammed Bin Rashid Al Maktoum City -District -1 Community
Units
31
Escrow bank
Dubai Islamic Bank
Name in Arabic
مدينة محمد بن راشد ال مكتوم ديستركت ون ، المرحلة الثالثة ، ريسيدنز 3
Project number
2000
Site inspections
6

Schedule

The register lists Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 3 as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%20182019202020212022
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

16 February 2022

100%+2.0 pts

  • Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 3 construction site, inspection photo 1, 16 February 2022
  • Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 3 construction site, inspection photo 2, 16 February 2022
  • Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 3 construction site, inspection photo 3, 16 February 2022
  • Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 3 construction site, inspection photo 4, 16 February 2022

5 December 2021

98%+1.3 pts

  • Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 3 construction site, inspection photo 1, 5 December 2021
  • Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 3 construction site, inspection photo 2, 5 December 2021
  • Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 3 construction site, inspection photo 3, 5 December 2021
  • Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 3 construction site, inspection photo 4, 5 December 2021

12 January 2021

97%+30 pts

  • Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 3 construction site, inspection photo 1, 12 January 2021
  • Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 3 construction site, inspection photo 2, 12 January 2021
  • Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 3 construction site, inspection photo 3, 12 January 2021
  • Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 3 construction site, inspection photo 4, 12 January 2021

22 January 2020

67%+56 pts

  • Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 3 construction site, inspection photo 1, 22 January 2020
  • Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 3 construction site, inspection photo 2, 22 January 2020
  • Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 3 construction site, inspection photo 3, 22 January 2020
  • Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 3 construction site, inspection photo 4, 22 January 2020

15 January 2019

10%+5.9 pts

  • Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 3 construction site, inspection photo 1, 15 January 2019
  • Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 3 construction site, inspection photo 2, 15 January 2019
  • Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 3 construction site, inspection photo 3, 15 January 2019
  • Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 3 construction site, inspection photo 4, 15 January 2019

8 August 2018

4.6%

  • Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 3 construction site, inspection photo 1, 8 August 2018
  • Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 3 construction site, inspection photo 2, 8 August 2018

All 50 site photos, by inspection date

Context

District One has 1 project under construction in Dubai, none past their registered completion dates.

Own a unit in Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 3?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 3 handover date?
Construction of Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 3 is recorded as complete, with a registered completion date of January 2022. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 3?
Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 3 was 100% built at the site inspection on 16 February 2022. The site has been inspected 6 times since August 2018. The Land Department took 50 site photos at its inspections.
Is Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 3 delayed?
The register lists construction as complete.
Who is building Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 3?
The registered developer is District One. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 3?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.