Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 14 construction progress

The register lists Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 14 in Mohammed Bin Rashid Al Maktoum City -District -1 Community as complete, with a registered completion date of March 2023. Its last site inspection on record was in August 2023. The developer is District One.

100%

Built, at the site inspection of 31 August 2023

Construction complete

Registered completion date
March 2023
Construction started
September 2018
First registered
April 2018
Developer
District One
Community
Mohammed Bin Rashid Al Maktoum City -District -1 Community
Units
136
Escrow bank
Dubai Islamic Bank
Name in Arabic
مدينة محمد بن راشد ال مكتوم ديستركت ون ، المرحلة الثالثة ، ريسيدنسز 14
Project number
2024
Site inspections
12

Schedule

The register lists Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 14 as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%20192020202120222023
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

31 August 2023

100%+2.9 pts

  • Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 14 construction site, inspection photo 1, 31 August 2023
  • Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 14 construction site, inspection photo 2, 31 August 2023
  • Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 14 construction site, inspection photo 3, 31 August 2023
  • Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 14 construction site, inspection photo 4, 31 August 2023

14 June 2023

97%+16 pts

  • Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 14 construction site, inspection photo 1, 14 June 2023
  • Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 14 construction site, inspection photo 2, 14 June 2023
  • Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 14 construction site, inspection photo 3, 14 June 2023
  • Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 14 construction site, inspection photo 4, 14 June 2023

4 January 2023

81%+10 pts

  • Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 14 construction site, inspection photo 1, 4 January 2023
  • Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 14 construction site, inspection photo 2, 4 January 2023
  • Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 14 construction site, inspection photo 3, 4 January 2023
  • Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 14 construction site, inspection photo 4, 4 January 2023

4 October 2022

71%+13 pts

  • Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 14 construction site, inspection photo 1, 4 October 2022
  • Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 14 construction site, inspection photo 2, 4 October 2022
  • Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 14 construction site, inspection photo 3, 4 October 2022
  • Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 14 construction site, inspection photo 4, 4 October 2022

20 June 2022

58%+2.9 pts

  • Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 14 construction site, inspection photo 1, 20 June 2022
  • Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 14 construction site, inspection photo 2, 20 June 2022
  • Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 14 construction site, inspection photo 3, 20 June 2022
  • Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 14 construction site, inspection photo 4, 20 June 2022

7 December 2021

55%+0.4 pts

  • Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 14 construction site, inspection photo 1, 7 December 2021
  • Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 14 construction site, inspection photo 2, 7 December 2021
  • Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 14 construction site, inspection photo 3, 7 December 2021
  • Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 14 construction site, inspection photo 4, 7 December 2021

9 December 2020

55%+13 pts

  • Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 14 construction site, inspection photo 1, 9 December 2020
  • Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 14 construction site, inspection photo 2, 9 December 2020
  • Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 14 construction site, inspection photo 3, 9 December 2020
  • Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 14 construction site, inspection photo 4, 9 December 2020

15 July 2020

42%+10 pts

  • Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 14 construction site, inspection photo 1, 15 July 2020
  • Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 14 construction site, inspection photo 2, 15 July 2020
  • Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 14 construction site, inspection photo 3, 15 July 2020
  • Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 14 construction site, inspection photo 4, 15 July 2020

8 April 2020

31%+11 pts

  • Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 14 construction site, inspection photo 1, 8 April 2020
  • Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 14 construction site, inspection photo 2, 8 April 2020
  • Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 14 construction site, inspection photo 3, 8 April 2020
  • Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 14 construction site, inspection photo 4, 8 April 2020

26 December 2019

20%+19 pts

  • Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 14 construction site, inspection photo 1, 26 December 2019
  • Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 14 construction site, inspection photo 2, 26 December 2019
  • Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 14 construction site, inspection photo 3, 26 December 2019
  • Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 14 construction site, inspection photo 4, 26 December 2019

All 108 site photos, by inspection date

Context

District One has 1 project under construction in Dubai, none past their registered completion dates.

Own a unit in Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 14?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 14 handover date?
Construction of Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 14 is recorded as complete, with a registered completion date of March 2023. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 14?
Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 14 was 100% built at the site inspection on 31 August 2023. The site has been inspected 12 times since August 2018. The Land Department took 108 site photos at its inspections.
Is Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 14 delayed?
The register lists construction as complete.
Who is building Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 14?
The registered developer is District One. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 14?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.