Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 14 construction progress
The register lists Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 14 in Mohammed Bin Rashid Al Maktoum City -District -1 Community as complete, with a registered completion date of March 2023. Its last site inspection on record was in August 2023. The developer is District One.
100%
Built, at the site inspection of 31 August 2023
Construction complete
- Registered completion date
- March 2023
- Construction started
- September 2018
- First registered
- April 2018
- Developer
- District One
- Community
- Mohammed Bin Rashid Al Maktoum City -District -1 Community
- Units
- 136
- Escrow bank
- Dubai Islamic Bank
- Name in Arabic
- مدينة محمد بن راشد ال مكتوم ديستركت ون ، المرحلة الثالثة ، ريسيدنسز 14
- Project number
- 2024
- Site inspections
- 12
Schedule
The register lists Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 14 as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.
Site inspections
31 August 2023
100%+2.9 pts
14 June 2023
97%+16 pts
4 January 2023
81%+10 pts
4 October 2022
71%+13 pts
20 June 2022
58%+2.9 pts
7 December 2021
55%+0.4 pts
9 December 2020
55%+13 pts
15 July 2020
42%+10 pts
8 April 2020
31%+11 pts
26 December 2019
20%+19 pts
Context
District One has 1 project under construction in Dubai, none past their registered completion dates.
Own a unit in Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 14?
The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.
Notify me when it launchesQuestions
- When is the Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 14 handover date?
- Construction of Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 14 is recorded as complete, with a registered completion date of March 2023. Handover of individual units follows on the developer's schedule, which the register does not show.
- What is the latest construction update on Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 14?
- Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 14 was 100% built at the site inspection on 31 August 2023. The site has been inspected 12 times since August 2018. The Land Department took 108 site photos at its inspections.
- Is Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 14 delayed?
- The register lists construction as complete.
- Who is building Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 14?
- The registered developer is District One. It has 1 other project under construction in Dubai.
- Which bank holds the escrow account for Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 14?
- Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Naya At District OneAlso by District One. 68%, Due September 2027.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)