Port De La Mer - Le Pont construction progress

The register lists Port De La Mer - Le Pont in La Mer as complete, with a registered completion date of July 2022. Its last site inspection on record was in July 2022. The developer is Pdlm Residential.

100%

Built, at the site inspection of 20 July 2022

Construction complete

Registered completion date
July 2022
Construction started
June 2019
First registered
April 2019
Developer
Pdlm Residential
Community
La Mer
Units
155
Escrow bank
Dubai Islamic Bank
Name in Arabic
لو بون - بورت دو لامير
Project number
2153
Site inspections
5

Schedule

The register lists Port De La Mer - Le Pont as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%202020212022
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

20 July 2022

100%+40 pts

  • Port De La Mer - Le Pont construction site, inspection photo 1, 20 July 2022
  • Port De La Mer - Le Pont construction site, inspection photo 2, 20 July 2022
  • Port De La Mer - Le Pont construction site, inspection photo 3, 20 July 2022
  • Port De La Mer - Le Pont construction site, inspection photo 4, 20 July 2022

16 December 2021

60%+27 pts

  • Port De La Mer - Le Pont construction site, inspection photo 1, 16 December 2021
  • Port De La Mer - Le Pont construction site, inspection photo 2, 16 December 2021
  • Port De La Mer - Le Pont construction site, inspection photo 3, 16 December 2021
  • Port De La Mer - Le Pont construction site, inspection photo 4, 16 December 2021

5 July 2021

33%+26 pts

  • Port De La Mer - Le Pont construction site, inspection photo 1, 5 July 2021
  • Port De La Mer - Le Pont construction site, inspection photo 2, 5 July 2021
  • Port De La Mer - Le Pont construction site, inspection photo 3, 5 July 2021
  • Port De La Mer - Le Pont construction site, inspection photo 4, 5 July 2021

16 April 2020

6.5%+3.9 pts

  • Port De La Mer - Le Pont construction site, inspection photo 1, 16 April 2020
  • Port De La Mer - Le Pont construction site, inspection photo 2, 16 April 2020
  • Port De La Mer - Le Pont construction site, inspection photo 3, 16 April 2020
  • Port De La Mer - Le Pont construction site, inspection photo 4, 16 April 2020

22 December 2019

2.6%

  • Port De La Mer - Le Pont construction site, inspection photo 1, 22 December 2019
  • Port De La Mer - Le Pont construction site, inspection photo 2, 22 December 2019
  • Port De La Mer - Le Pont construction site, inspection photo 3, 22 December 2019
  • Port De La Mer - Le Pont construction site, inspection photo 4, 22 December 2019

All 47 site photos, by inspection date

Context

La Mer has 5 projects under construction, 1.0% built on average.

Own a unit in Port De La Mer - Le Pont?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Port De La Mer - Le Pont handover date?
Construction of Port De La Mer - Le Pont is recorded as complete, with a registered completion date of July 2022. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Port De La Mer - Le Pont?
Port De La Mer - Le Pont was 100% built at the site inspection on 20 July 2022. The site has been inspected 5 times since December 2019. The Land Department took 47 site photos at its inspections.
Is Port De La Mer - Le Pont delayed?
The register lists construction as complete.
Who is building Port De La Mer - Le Pont?
The registered developer is Pdlm Residential.
Which bank holds the escrow account for Port De La Mer - Le Pont?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.