Port De La Mer - La Voile construction progress

The register lists Port De La Mer - La Voile in La Mer as complete, with a registered completion date of April 2022. Its last site inspection on record was in April 2023. The developer is Pdlm Residential.

100%

Built, at the site inspection of 11 April 2023

Construction complete

Registered completion date
April 2022
Construction started
December 2019
First registered
October 2019
Developer
Pdlm Residential
Community
La Mer
Units
183
Escrow bank
Dubai Islamic Bank
Name in Arabic
بورت دي لا مير - لا فوال
Project number
2181
Site inspections
6

Schedule

The register lists Port De La Mer - La Voile as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2020202120222023
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

11 April 2023

100%+19 pts

  • Port De La Mer - La Voile construction site, inspection photo 1, 11 April 2023
  • Port De La Mer - La Voile construction site, inspection photo 2, 11 April 2023
  • Port De La Mer - La Voile construction site, inspection photo 3, 11 April 2023
  • Port De La Mer - La Voile construction site, inspection photo 4, 11 April 2023

6 November 2022

81%+33 pts

  • Port De La Mer - La Voile construction site, inspection photo 1, 6 November 2022
  • Port De La Mer - La Voile construction site, inspection photo 2, 6 November 2022
  • Port De La Mer - La Voile construction site, inspection photo 3, 6 November 2022
  • Port De La Mer - La Voile construction site, inspection photo 4, 6 November 2022

23 May 2022

48%+24 pts

  • Port De La Mer - La Voile construction site, inspection photo 1, 23 May 2022
  • Port De La Mer - La Voile construction site, inspection photo 2, 23 May 2022
  • Port De La Mer - La Voile construction site, inspection photo 3, 23 May 2022
  • Port De La Mer - La Voile construction site, inspection photo 4, 23 May 2022

20 October 2021

25%+18 pts

  • Port De La Mer - La Voile construction site, inspection photo 1, 20 October 2021
  • Port De La Mer - La Voile construction site, inspection photo 2, 20 October 2021
  • Port De La Mer - La Voile construction site, inspection photo 3, 20 October 2021
  • Port De La Mer - La Voile construction site, inspection photo 4, 20 October 2021

19 August 2020

6.4%+3.2 pts

  • Port De La Mer - La Voile construction site, inspection photo 1, 19 August 2020
  • Port De La Mer - La Voile construction site, inspection photo 2, 19 August 2020
  • Port De La Mer - La Voile construction site, inspection photo 3, 19 August 2020
  • Port De La Mer - La Voile construction site, inspection photo 4, 19 August 2020

16 April 2020

3.2%

  • Port De La Mer - La Voile construction site, inspection photo 1, 16 April 2020
  • Port De La Mer - La Voile construction site, inspection photo 2, 16 April 2020
  • Port De La Mer - La Voile construction site, inspection photo 3, 16 April 2020
  • Port De La Mer - La Voile construction site, inspection photo 4, 16 April 2020

All 59 site photos, by inspection date

Context

La Mer has 5 projects under construction, 1.0% built on average.

Own a unit in Port De La Mer - La Voile?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Port De La Mer - La Voile handover date?
Construction of Port De La Mer - La Voile is recorded as complete, with a registered completion date of April 2022. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Port De La Mer - La Voile?
Port De La Mer - La Voile was 100% built at the site inspection on 11 April 2023. The site has been inspected 6 times since April 2020. The Land Department took 59 site photos at its inspections.
Is Port De La Mer - La Voile delayed?
The register lists construction as complete.
Who is building Port De La Mer - La Voile?
The registered developer is Pdlm Residential.
Which bank holds the escrow account for Port De La Mer - La Voile?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.