Port De La Mer - La Cote construction progress
The register lists Port De La Mer - La Cote in La Mer as complete, with a registered completion date of September 2021. Its last site inspection on record was in September 2021. The developer is Pdlm Residential.
100%
Built, at the site inspection of 30 September 2021
Construction complete
- Registered completion date
- September 2021
- Construction started
- March 2019
- First registered
- September 2018
- Developer
- Pdlm Residential
- Community
- La Mer
- Units
- 429
- Escrow bank
- Dubai Islamic Bank
- Name in Arabic
- بورت دو لامير - لا كوت
- Project number
- 2093
- Site inspections
- 7
Schedule
The register lists Port De La Mer - La Cote as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.
Site inspections
30 September 2021
100%+1.9 pts
2 August 2021
98%+9.9 pts
18 January 2021
88%+35 pts
18 June 2020
53%+16 pts
15 February 2020
37%+25 pts
11 September 2019
13%+6.1 pts
9 April 2019
6.4%
Context
La Mer has 5 projects under construction, 1.0% built on average.
Own a unit in Port De La Mer - La Cote?
The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.
Notify me when it launchesQuestions
- When is the Port De La Mer - La Cote handover date?
- Construction of Port De La Mer - La Cote is recorded as complete, with a registered completion date of September 2021. Handover of individual units follows on the developer's schedule, which the register does not show.
- What is the latest construction update on Port De La Mer - La Cote?
- Port De La Mer - La Cote was 100% built at the site inspection on 30 September 2021. The site has been inspected 7 times since April 2019. The Land Department took 68 site photos at its inspections.
- Is Port De La Mer - La Cote delayed?
- The register lists construction as complete.
- Who is building Port De La Mer - La Cote?
- The registered developer is Pdlm Residential.
- Which bank holds the escrow account for Port De La Mer - La Cote?
- Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Jumeirah Asora BayNearby in La Mer. 4.4%, Due March 2029.
- Jumeirah Residences - Asora Bay - Ocean MansionsNearby in La Mer. 0.5%, Due March 2029.
- Solaya (1,2,3)Nearby in La Mer. 0%, Due June 2029.
- Solaya (4,6)Nearby in La Mer. 0%, Due September 2029.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)



.jpg&w=3840&q=75)