Jumeirah Gate construction photos
90 photos from 10 site inspections, newest first. The percentage is how much of Jumeirah Gate was built on the day of each visit.
23 March 2021100% built
21 October 202086% built
2 July 202077% built
22 January 202070% built
10 July 201947% built
31 January 201930% built
24 September 201823% built
9 April 201816% built
23 November 20178.6% built
19 April 20173.6% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.