Jumeirah Gate construction progress

The register lists Jumeirah Gate in Jumeriah Beach Residence - Jbr as complete, with a registered completion date of March 2021. Its last site inspection on record was in March 2021. The developer is Al Aseel Investments.

100%

Built, at the site inspection of 23 March 2021

Construction complete

Registered completion date
March 2021
Construction started
September 2016
First registered
September 2016
Developer
Al Aseel Investments
Community
Jumeriah Beach Residence - Jbr
Units
920
Escrow bank
First Abu Dhabi Bank
Name in Arabic
جميرا غيت
Project number
1790
Site inspections
10

Schedule

The register lists Jumeirah Gate as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%20172018201920202021
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

23 March 2021

100%+14 pts

  • Jumeirah Gate construction site, inspection photo 1, 23 March 2021
  • Jumeirah Gate construction site, inspection photo 2, 23 March 2021
  • Jumeirah Gate construction site, inspection photo 3, 23 March 2021
  • Jumeirah Gate construction site, inspection photo 4, 23 March 2021

21 October 2020

86%+8.9 pts

  • Jumeirah Gate construction site, inspection photo 1, 21 October 2020
  • Jumeirah Gate construction site, inspection photo 2, 21 October 2020
  • Jumeirah Gate construction site, inspection photo 3, 21 October 2020
  • Jumeirah Gate construction site, inspection photo 4, 21 October 2020

2 July 2020

77%+7.3 pts

  • Jumeirah Gate construction site, inspection photo 1, 2 July 2020
  • Jumeirah Gate construction site, inspection photo 2, 2 July 2020
  • Jumeirah Gate construction site, inspection photo 3, 2 July 2020
  • Jumeirah Gate construction site, inspection photo 4, 2 July 2020

22 January 2020

70%+23 pts

  • Jumeirah Gate construction site, inspection photo 1, 22 January 2020
  • Jumeirah Gate construction site, inspection photo 2, 22 January 2020
  • Jumeirah Gate construction site, inspection photo 3, 22 January 2020
  • Jumeirah Gate construction site, inspection photo 4, 22 January 2020

10 July 2019

47%+17 pts

  • Jumeirah Gate construction site, inspection photo 1, 10 July 2019
  • Jumeirah Gate construction site, inspection photo 2, 10 July 2019
  • Jumeirah Gate construction site, inspection photo 3, 10 July 2019
  • Jumeirah Gate construction site, inspection photo 4, 10 July 2019

31 January 2019

30%+7.1 pts

  • Jumeirah Gate construction site, inspection photo 1, 31 January 2019
  • Jumeirah Gate construction site, inspection photo 2, 31 January 2019
  • Jumeirah Gate construction site, inspection photo 3, 31 January 2019
  • Jumeirah Gate construction site, inspection photo 4, 31 January 2019

24 September 2018

23%+6.9 pts

  • Jumeirah Gate construction site, inspection photo 1, 24 September 2018
  • Jumeirah Gate construction site, inspection photo 2, 24 September 2018
  • Jumeirah Gate construction site, inspection photo 3, 24 September 2018
  • Jumeirah Gate construction site, inspection photo 4, 24 September 2018

9 April 2018

16%+7.5 pts

  • Jumeirah Gate construction site, inspection photo 1, 9 April 2018
  • Jumeirah Gate construction site, inspection photo 2, 9 April 2018
  • Jumeirah Gate construction site, inspection photo 3, 9 April 2018
  • Jumeirah Gate construction site, inspection photo 4, 9 April 2018

23 November 2017

8.6%+5.0 pts

  • Jumeirah Gate construction site, inspection photo 1, 23 November 2017
  • Jumeirah Gate construction site, inspection photo 2, 23 November 2017
  • Jumeirah Gate construction site, inspection photo 3, 23 November 2017

19 April 2017

3.6%

  • Jumeirah Gate construction site, inspection photo 1, 19 April 2017
  • Jumeirah Gate construction site, inspection photo 2, 19 April 2017
  • Jumeirah Gate construction site, inspection photo 3, 19 April 2017

All 90 site photos, by inspection date

Own a unit in Jumeirah Gate?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Jumeirah Gate handover date?
Construction of Jumeirah Gate is recorded as complete, with a registered completion date of March 2021. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Jumeirah Gate?
Jumeirah Gate was 100% built at the site inspection on 23 March 2021. The site has been inspected 10 times since April 2017. The Land Department took 90 site photos at its inspections.
Is Jumeirah Gate delayed?
The register lists construction as complete.
Who is building Jumeirah Gate?
The registered developer is Al Aseel Investments.
Which bank holds the escrow account for Jumeirah Gate?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.