Jumeirah Gate construction progress
The register lists Jumeirah Gate in Jumeriah Beach Residence - Jbr as complete, with a registered completion date of March 2021. Its last site inspection on record was in March 2021. The developer is Al Aseel Investments.
100%
Built, at the site inspection of 23 March 2021
Construction complete
- Registered completion date
- March 2021
- Construction started
- September 2016
- First registered
- September 2016
- Developer
- Al Aseel Investments
- Community
- Jumeriah Beach Residence - Jbr
- Units
- 920
- Escrow bank
- First Abu Dhabi Bank
- Name in Arabic
- جميرا غيت
- Project number
- 1790
- Site inspections
- 10
Schedule
The register lists Jumeirah Gate as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.
Site inspections
23 March 2021
100%+14 pts
21 October 2020
86%+8.9 pts
2 July 2020
77%+7.3 pts
22 January 2020
70%+23 pts
10 July 2019
47%+17 pts
31 January 2019
30%+7.1 pts
24 September 2018
23%+6.9 pts
9 April 2018
16%+7.5 pts
23 November 2017
8.6%+5.0 pts
19 April 2017
3.6%
Own a unit in Jumeirah Gate?
The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.
Notify me when it launchesQuestions
- When is the Jumeirah Gate handover date?
- Construction of Jumeirah Gate is recorded as complete, with a registered completion date of March 2021. Handover of individual units follows on the developer's schedule, which the register does not show.
- What is the latest construction update on Jumeirah Gate?
- Jumeirah Gate was 100% built at the site inspection on 23 March 2021. The site has been inspected 10 times since April 2017. The Land Department took 90 site photos at its inspections.
- Is Jumeirah Gate delayed?
- The register lists construction as complete.
- Who is building Jumeirah Gate?
- The registered developer is Al Aseel Investments.
- Which bank holds the escrow account for Jumeirah Gate?
- First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.