Peninsula Dubai Residences - Tower 2 construction progress

Peninsula Dubai Residences - Tower 2 in Jumeirah Second is 6.0% built at the Land Department inspection of August 2026. Developer Dubai Peninsula. Completion registered for January 2029.

6.0%

Built, at the Land Department site inspection of 13 August 2026

Running behind its date

Completion date (Land Department)
January 2029
Finish at recent pace
May 2042
Construction started
March 2025
Registered with the Land Department
April 2025
Developer
Dubai Peninsula
Units
102
Escrow bank
Emirates NBD
Name in Arabic
بننسيولا دبي ريزيدنسز - برج 2
Land Department project number
3548
Land Department site inspections
4

Schedule

Between August 2025 and August 2026 the site added about 0.5 points a month. At that rate it would finish around May 2042, more than three months after the January 2029 date registered with the Land Department.

0%25%50%75%100%2026202720282029
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

13 August 2026

6.0%+2.0 pts

  • Peninsula Dubai Residences - Tower 2 construction site, Land Department inspection photo 1, 13 August 2026
  • Peninsula Dubai Residences - Tower 2 construction site, Land Department inspection photo 2, 13 August 2026
  • Peninsula Dubai Residences - Tower 2 construction site, Land Department inspection photo 3, 13 August 2026
  • Peninsula Dubai Residences - Tower 2 construction site, Land Department inspection photo 4, 13 August 2026

7 May 2026

4.0%+3.8 pts

  • Peninsula Dubai Residences - Tower 2 construction site, Land Department inspection photo 1, 7 May 2026
  • Peninsula Dubai Residences - Tower 2 construction site, Land Department inspection photo 2, 7 May 2026
  • Peninsula Dubai Residences - Tower 2 construction site, Land Department inspection photo 3, 7 May 2026
  • Peninsula Dubai Residences - Tower 2 construction site, Land Department inspection photo 4, 7 May 2026

20 August 2025

0.1%+0.1 pts

  • Peninsula Dubai Residences - Tower 2 construction site, Land Department inspection photo 1, 20 August 2025
  • Peninsula Dubai Residences - Tower 2 construction site, Land Department inspection photo 2, 20 August 2025
  • Peninsula Dubai Residences - Tower 2 construction site, Land Department inspection photo 3, 20 August 2025
  • Peninsula Dubai Residences - Tower 2 construction site, Land Department inspection photo 4, 20 August 2025

10 February 2025

0%

  • Peninsula Dubai Residences - Tower 2 construction site, Land Department inspection photo 1, 10 February 2025
  • Peninsula Dubai Residences - Tower 2 construction site, Land Department inspection photo 2, 10 February 2025

All 15 site photos, by inspection date

Context

Jumeirah Second has 4 projects under construction, 3.1% built on average.

Dubai Peninsula has 2 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Peninsula Dubai Residences - Tower 2?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Peninsula Dubai Residences - Tower 2 be completed?
The completion date registered with the Dubai Land Department is January 2029. At the pace of its recent inspections the site would reach 100% around May 2042. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Peninsula Dubai Residences - Tower 2 is built?
6.0%, measured at the Land Department site inspection on 13 August 2026. The Land Department engineers have inspected the site 4 times since February 2025.
Is Peninsula Dubai Residences - Tower 2 delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of January 2029.
Who is building Peninsula Dubai Residences - Tower 2?
The registered developer is Dubai Peninsula. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Peninsula Dubai Residences - Tower 2?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.