Aman Residences Dubai construction progress

Aman Residences Dubai in Jumeirah Second is 0.9% built at the Land Department inspection of August 2026. Developer Blackwood Development. Completion registered for December 2028.

0.9%

Built, at the Land Department site inspection of 10 August 2026

Running behind its date

Completion date (Land Department)
December 2028
Finish at recent pace
February 2059
Construction started
July 2025
Registered with the Land Department
January 2025
Developer
Blackwood Development
Units
82
Escrow bank
Emirates NBD
Name in Arabic
آمان رزيدنسز دبي
Land Department project number
3461
Land Department site inspections
2

Schedule

Between April 2026 and August 2026 the site added about 0.3 points a month. At that rate it would finish around February 2059, more than three months after the December 2028 date registered with the Land Department.

0%25%50%75%100%202620272028
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

10 August 2026

0.9%+0.9 pts

  • Aman Residences Dubai construction site, Land Department inspection photo 1, 10 August 2026
  • Aman Residences Dubai construction site, Land Department inspection photo 2, 10 August 2026
  • Aman Residences Dubai construction site, Land Department inspection photo 3, 10 August 2026
  • Aman Residences Dubai construction site, Land Department inspection photo 4, 10 August 2026

24 April 2026

0%

  • Aman Residences Dubai construction site, Land Department inspection photo 1, 24 April 2026
  • Aman Residences Dubai construction site, Land Department inspection photo 2, 24 April 2026
  • Aman Residences Dubai construction site, Land Department inspection photo 3, 24 April 2026

All 8 site photos, by inspection date

Context

Jumeirah Second has 4 projects under construction, 3.1% built on average.

Own a unit in Aman Residences Dubai?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Aman Residences Dubai be completed?
The completion date registered with the Dubai Land Department is December 2028. At the pace of its recent inspections the site would reach 100% around February 2059. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Aman Residences Dubai is built?
0.9%, measured at the Land Department site inspection on 10 August 2026. The Land Department engineers have inspected the site 2 times since April 2026.
Is Aman Residences Dubai delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2028.
Who is building Aman Residences Dubai?
The registered developer is Blackwood Development.
Which bank holds the escrow account for Aman Residences Dubai?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.