Aman Residences Dubai construction progress

The registered completion date for Aman Residences Dubai in Jumeirah Second is December 2028. At the last site inspection, in November 2026, it was 2.9% built. The developer is Blackwood Development.

2.9%

Built, at the site inspection of 6 November 2026

Running behind its date

Registered completion date
December 2028
Finish at recent pace
February 2045
Construction started
July 2025
First registered
January 2025
Developer
Blackwood Development
Units
82
Escrow bank
Emirates NBD
Name in Arabic
آمان رزيدنسز دبي
Project number
3461
Site inspections
3

Schedule

Between April 2026 and November 2026 the site added about 0.4 points a month. At that rate it would finish around February 2045, more than three months after its registered date of December 2028.

0%25%50%75%100%202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

6 November 2026

2.9%+2.0 pts

  • Aman Residences Dubai construction site, inspection photo 1, 6 November 2026
  • Aman Residences Dubai construction site, inspection photo 2, 6 November 2026
  • Aman Residences Dubai construction site, inspection photo 3, 6 November 2026
  • Aman Residences Dubai construction site, inspection photo 4, 6 November 2026

10 August 2026

0.9%+0.9 pts

  • Aman Residences Dubai construction site, inspection photo 1, 10 August 2026
  • Aman Residences Dubai construction site, inspection photo 2, 10 August 2026
  • Aman Residences Dubai construction site, inspection photo 3, 10 August 2026
  • Aman Residences Dubai construction site, inspection photo 4, 10 August 2026

24 April 2026

0%

  • Aman Residences Dubai construction site, inspection photo 1, 24 April 2026
  • Aman Residences Dubai construction site, inspection photo 2, 24 April 2026
  • Aman Residences Dubai construction site, inspection photo 3, 24 April 2026

All 13 site photos, by inspection date

Context

Jumeirah Second has 4 projects under construction, 3.7% built on average.

Own a unit in Aman Residences Dubai?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Aman Residences Dubai handover date?
The registered completion date is December 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around February 2045. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Aman Residences Dubai?
Aman Residences Dubai was 2.9% built at the site inspection on 6 November 2026. The site has been inspected 3 times since April 2026. The Land Department took 13 site photos at its inspections.
Is Aman Residences Dubai delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2028.
Who is building Aman Residences Dubai?
The registered developer is Blackwood Development.
Which bank holds the escrow account for Aman Residences Dubai?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.