Pinewood Estate Homes construction progress
Pinewood Estate Homes in Jumeirah Golf Estates - Phase B is 0.3% built at the Land Department inspection of March 2026. Developer Jge Real Estate. Completion registered for November 2028.
0.3%
Built, at the Land Department site inspection of 11 March 2026
Running behind its date
- Completion date (Land Department)
- November 2028
- Finish at recent pace
- October 2254
- Construction started
- March 2026
- Registered with the Land Department
- June 2025
- Developer
- Jge Real Estate
- Community
- Jumeirah Golf Estates - Phase B
- Units
- 247
- Escrow bank
- Emirates NBD
- Name in Arabic
- باينوود استيت هومز
- Land Department project number
- 3832
- Land Department site inspections
- 2
Schedule
Between June 2025 and March 2026 the site added about 0.0 points a month. At that rate it would finish around October 2254, more than three months after the November 2028 date registered with the Land Department.
Site inspections
11 March 2026
0.3%+0.3 pts
16 June 2025
0%
Context
Jumeirah Golf Estates - Phase B has 2 projects under construction, 0.2% built on average.
Jge Real Estate has 4 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Pinewood Estate Homes?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Pinewood Estate Homes be completed?
- The completion date registered with the Dubai Land Department is November 2028. At the pace of its recent inspections the site would reach 100% around October 2254. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Pinewood Estate Homes is built?
- 0.3%, measured at the Land Department site inspection on 11 March 2026. The Land Department engineers have inspected the site 2 times since June 2025.
- Is Pinewood Estate Homes delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of November 2028.
- Who is building Pinewood Estate Homes?
- The registered developer is Jge Real Estate. It has 3 other projects under construction in Dubai.
- Which bank holds the escrow account for Pinewood Estate Homes?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Ashwood EstatesAlso by Jge Real Estate. 0.1%, Due September 2028.
- Cedarwood EstatesAlso by Jge Real Estate. 0%, Due October 2028.
- Cedarwood Estates-SouthAlso by Jge Real Estate. 0%.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.