Ashwood Estates construction progress

Ashwood Estates in Jumeirah Golf Estates - Phase B is 0.1% built at the Land Department inspection of June 2026. Developer Jge Real Estate. Completion registered for September 2028.

0.1%

Built, at the Land Department site inspection of 1 June 2026

Running behind its date

Completion date (Land Department)
September 2028
Finish at recent pace
November 3558
Construction started
August 2025
Registered with the Land Department
September 2025
Community
Jumeirah Golf Estates - Phase B
Units
187
Escrow bank
Emirates NBD
Name in Arabic
آش وود استيتس
Land Department project number
4029
Land Department site inspections
2

Schedule

Between August 2025 and June 2026 the site added about 0.0 points a month. At that rate it would finish around November 3558, more than three months after the September 2028 date registered with the Land Department.

0%25%50%75%100%202620272028
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

1 June 2026

0.1%+0.1 pts

  • Ashwood Estates construction site, Land Department inspection photo 1, 1 June 2026
  • Ashwood Estates construction site, Land Department inspection photo 2, 1 June 2026
  • Ashwood Estates construction site, Land Department inspection photo 3, 1 June 2026

25 August 2025

0%

  • Ashwood Estates construction site, Land Department inspection photo 1, 25 August 2025
  • Ashwood Estates construction site, Land Department inspection photo 2, 25 August 2025

All 5 site photos, by inspection date

Context

Jumeirah Golf Estates - Phase B has 2 projects under construction, 0.2% built on average. Ashwood Estates is behind that average.

Jge Real Estate has 4 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Ashwood Estates?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Track the handover

Questions

When will Ashwood Estates be completed?
The completion date registered with the Dubai Land Department is September 2028. At the pace of its recent inspections the site would reach 100% around November 3558. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Ashwood Estates is built?
0.1%, measured at the Land Department site inspection on 1 June 2026. The Land Department engineers have inspected the site 2 times since August 2025.
Is Ashwood Estates delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of September 2028.
Who is building Ashwood Estates?
The registered developer is Jge Real Estate. It has 3 other projects under construction in Dubai.
Which bank holds the escrow account for Ashwood Estates?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.