The register lists The Pearl in Jaddaf Waterfront as complete, with a registered completion date of March 2020. Its last site inspection on record was in March 2020. The developer is Alshafar Development.

100%

Built, at the site inspection of 25 March 2020

Construction complete

Registered completion date
March 2020
Construction started
March 2013
First registered
November 2008
Developer
Alshafar Development
Units
61
Escrow bank
Dubai Islamic Bank
Name in Arabic
ذا بيرل
Project number
506
Site inspections
8

Schedule

The register lists The Pearl as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2014201620182020
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

25 March 2020

100%+3.2 pts

  • The Pearl construction site, inspection photo 1, 25 March 2020
  • The Pearl construction site, inspection photo 2, 25 March 2020
  • The Pearl construction site, inspection photo 3, 25 March 2020
  • The Pearl construction site, inspection photo 4, 25 March 2020

26 November 2018

97%+5.0 pts

  • The Pearl construction site, inspection photo 1, 26 November 2018
  • The Pearl construction site, inspection photo 2, 26 November 2018
  • The Pearl construction site, inspection photo 3, 26 November 2018
  • The Pearl construction site, inspection photo 4, 26 November 2018

7 January 2018

92%+1.7 pts

  • The Pearl construction site, inspection photo 1, 7 January 2018
  • The Pearl construction site, inspection photo 2, 7 January 2018
  • The Pearl construction site, inspection photo 3, 7 January 2018
  • The Pearl construction site, inspection photo 4, 7 January 2018

6 June 2017

90%+24 pts

  • The Pearl construction site, inspection photo 1, 6 June 2017
  • The Pearl construction site, inspection photo 2, 6 June 2017
  • The Pearl construction site, inspection photo 3, 6 June 2017
  • The Pearl construction site, inspection photo 4, 6 June 2017

6 October 2015

67%+29 pts

  • The Pearl construction site, inspection photo 1, 6 October 2015
  • The Pearl construction site, inspection photo 2, 6 October 2015
  • The Pearl construction site, inspection photo 3, 6 October 2015

1 December 2014

38%+20 pts

  • The Pearl construction site, inspection photo 1, 1 December 2014
  • The Pearl construction site, inspection photo 2, 1 December 2014
  • The Pearl construction site, inspection photo 3, 1 December 2014
  • The Pearl construction site, inspection photo 4, 1 December 2014

16 March 2014

18%+13 pts

  • The Pearl construction site, inspection photo 1, 16 March 2014
  • The Pearl construction site, inspection photo 2, 16 March 2014
  • The Pearl construction site, inspection photo 3, 16 March 2014
  • The Pearl construction site, inspection photo 4, 16 March 2014

23 September 2013

4.5%

  • The Pearl construction site, inspection photo 1, 23 September 2013
  • The Pearl construction site, inspection photo 2, 23 September 2013
  • The Pearl construction site, inspection photo 3, 23 September 2013
  • The Pearl construction site, inspection photo 4, 23 September 2013

All 64 site photos, by inspection date

Context

Jaddaf Waterfront has 13 projects under construction, 32% built on average.

Own a unit in The Pearl?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the The Pearl handover date?
Construction of The Pearl is recorded as complete, with a registered completion date of March 2020. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on The Pearl?
The Pearl was 100% built at the site inspection on 25 March 2020. The site has been inspected 8 times since September 2013. The Land Department took 64 site photos at its inspections.
Is The Pearl delayed?
The register lists construction as complete.
Who is building The Pearl?
The registered developer is Alshafar Development.
Which bank holds the escrow account for The Pearl?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.