Riah Towers construction progress

The register lists Riah Towers in Jaddaf Waterfront as complete, with a registered completion date of December 2016. Its last site inspection on record was in September 2017. The developer is Radiant Star Properties.

100%

Built, at the site inspection of 14 September 2017

Construction complete

Registered completion date
December 2016
Construction started
September 2013
First registered
May 2015
Developer
Radiant Star Properties
Units
160
Escrow bank
Commercial Bank International
Name in Arabic
براج ريا
Project number
1658
Site inspections
4

Schedule

The register lists Riah Towers as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2014201520162017
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

14 September 2017

100%+19 pts

  • Riah Towers construction site, inspection photo 1, 14 September 2017
  • Riah Towers construction site, inspection photo 2, 14 September 2017
  • Riah Towers construction site, inspection photo 3, 14 September 2017
  • Riah Towers construction site, inspection photo 4, 14 September 2017

8 November 2016

81%+18 pts

  • Riah Towers construction site, inspection photo 1, 8 November 2016
  • Riah Towers construction site, inspection photo 2, 8 November 2016
  • Riah Towers construction site, inspection photo 3, 8 November 2016
  • Riah Towers construction site, inspection photo 4, 8 November 2016

29 March 2016

63%+22 pts

  • Riah Towers construction site, inspection photo 1, 29 March 2016
  • Riah Towers construction site, inspection photo 2, 29 March 2016
  • Riah Towers construction site, inspection photo 3, 29 March 2016
  • Riah Towers construction site, inspection photo 4, 29 March 2016

2 July 2015

41%

  • Riah Towers construction site, inspection photo 1, 2 July 2015
  • Riah Towers construction site, inspection photo 2, 2 July 2015
  • Riah Towers construction site, inspection photo 3, 2 July 2015
  • Riah Towers construction site, inspection photo 4, 2 July 2015

All 35 site photos, by inspection date

Context

Jaddaf Waterfront has 13 projects under construction, 32% built on average.

Own a unit in Riah Towers?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Riah Towers handover date?
Construction of Riah Towers is recorded as complete, with a registered completion date of December 2016. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Riah Towers?
Riah Towers was 100% built at the site inspection on 14 September 2017. The site has been inspected 4 times since July 2015. The Land Department took 35 site photos at its inspections.
Is Riah Towers delayed?
The register lists construction as complete.
Who is building Riah Towers?
The registered developer is Radiant Star Properties.
Which bank holds the escrow account for Riah Towers?
Commercial Bank International. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.