Niloofar construction progress

The register lists Niloofar in Jaddaf Waterfront as complete, with a registered completion date of May 2017. Its last site inspection on record was in October 2017. The developer is Rmg Limited.

100%

Built, at the site inspection of 4 October 2017

Construction complete

Registered completion date
May 2017
Construction started
February 2008
First registered
November 2008
Developer
Rmg Limited
Units
94
Escrow bank
Dubai Islamic Bank
Name in Arabic
نيلوفر
Project number
146
Site inspections
11

Schedule

The register lists Niloofar as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%20092011201320152017
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

4 October 2017

100%+0.8 pts

  • Niloofar construction site, inspection photo 1, 4 October 2017
  • Niloofar construction site, inspection photo 2, 4 October 2017
  • Niloofar construction site, inspection photo 3, 4 October 2017
  • Niloofar construction site, inspection photo 4, 4 October 2017

17 July 2017

99%+3.5 pts

  • Niloofar construction site, inspection photo 1, 17 July 2017
  • Niloofar construction site, inspection photo 2, 17 July 2017
  • Niloofar construction site, inspection photo 3, 17 July 2017
  • Niloofar construction site, inspection photo 4, 17 July 2017

17 August 2016

96%+4.5 pts

  • Niloofar construction site, inspection photo 1, 17 August 2016
  • Niloofar construction site, inspection photo 2, 17 August 2016
  • Niloofar construction site, inspection photo 3, 17 August 2016
  • Niloofar construction site, inspection photo 4, 17 August 2016

28 December 2015

91%+2.5 pts

  • Niloofar construction site, inspection photo 1, 28 December 2015
  • Niloofar construction site, inspection photo 2, 28 December 2015
  • Niloofar construction site, inspection photo 3, 28 December 2015

29 September 2015

89%+3.3 pts

  • Niloofar construction site, inspection photo 1, 29 September 2015
  • Niloofar construction site, inspection photo 2, 29 September 2015

18 December 2014

85%+1.3 pts

  • Niloofar construction site, inspection photo 1, 18 December 2014
  • Niloofar construction site, inspection photo 2, 18 December 2014
  • Niloofar construction site, inspection photo 3, 18 December 2014
  • Niloofar construction site, inspection photo 4, 18 December 2014

9 August 2014

84%+8.1 pts

  • Niloofar construction site, inspection photo 1, 9 August 2014
  • Niloofar construction site, inspection photo 2, 9 August 2014
  • Niloofar construction site, inspection photo 3, 9 August 2014
  • Niloofar construction site, inspection photo 4, 9 August 2014

31 March 2014

76%+5.0 pts

  • Niloofar construction site, inspection photo 1, 31 March 2014
  • Niloofar construction site, inspection photo 2, 31 March 2014
  • Niloofar construction site, inspection photo 3, 31 March 2014
  • Niloofar construction site, inspection photo 4, 31 March 2014

4 November 2013

71%+11 pts

  • Niloofar construction site, inspection photo 1, 4 November 2013
  • Niloofar construction site, inspection photo 2, 4 November 2013
  • Niloofar construction site, inspection photo 3, 4 November 2013
  • Niloofar construction site, inspection photo 4, 4 November 2013

27 May 2013

60%+4.5 pts

  • Niloofar construction site, inspection photo 1, 27 May 2013
  • Niloofar construction site, inspection photo 2, 27 May 2013
  • Niloofar construction site, inspection photo 3, 27 May 2013
  • Niloofar construction site, inspection photo 4, 27 May 2013

All 100 site photos, by inspection date

Context

Jaddaf Waterfront has 13 projects under construction, 32% built on average.

Own a unit in Niloofar?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Niloofar handover date?
Construction of Niloofar is recorded as complete, with a registered completion date of May 2017. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Niloofar?
Niloofar was 100% built at the site inspection on 4 October 2017. The site has been inspected 11 times since January 2013. The Land Department took 100 site photos at its inspections.
Is Niloofar delayed?
The register lists construction as complete.
Who is building Niloofar?
The registered developer is Rmg Limited.
Which bank holds the escrow account for Niloofar?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.