Nastaran Tower construction progress

The register lists Nastaran Tower in Jaddaf Waterfront as complete, with a registered completion date of November 2016. Its last site inspection on record was in November 2016. The developer is Raam Limited.

100%

Built, at the site inspection of 3 November 2016

Construction complete

Registered completion date
November 2016
Construction started
April 2008
First registered
November 2008
Developer
Raam Limited
Units
177
Escrow bank
Dubai Islamic Bank
Name in Arabic
ناستاران تاور
Project number
771
Site inspections
6

Schedule

The register lists Nastaran Tower as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2009201120132015
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

3 November 2016

100%+3.3 pts

  • Nastaran Tower construction site, inspection photo 1, 3 November 2016
  • Nastaran Tower construction site, inspection photo 2, 3 November 2016
  • Nastaran Tower construction site, inspection photo 3, 3 November 2016
  • Nastaran Tower construction site, inspection photo 4, 3 November 2016

2 March 2015

97%+2.7 pts

  • Nastaran Tower construction site, inspection photo 1, 2 March 2015
  • Nastaran Tower construction site, inspection photo 2, 2 March 2015
  • Nastaran Tower construction site, inspection photo 3, 2 March 2015
  • Nastaran Tower construction site, inspection photo 4, 2 March 2015

13 October 2014

94%+9.0 pts

  • Nastaran Tower construction site, inspection photo 1, 13 October 2014
  • Nastaran Tower construction site, inspection photo 2, 13 October 2014
  • Nastaran Tower construction site, inspection photo 3, 13 October 2014
  • Nastaran Tower construction site, inspection photo 4, 13 October 2014

19 February 2014

85%+4.7 pts

  • Nastaran Tower construction site, inspection photo 1, 19 February 2014
  • Nastaran Tower construction site, inspection photo 2, 19 February 2014
  • Nastaran Tower construction site, inspection photo 3, 19 February 2014
  • Nastaran Tower construction site, inspection photo 4, 19 February 2014

22 May 2013

80%+23 pts

  • Nastaran Tower construction site, inspection photo 1, 22 May 2013
  • Nastaran Tower construction site, inspection photo 2, 22 May 2013
  • Nastaran Tower construction site, inspection photo 3, 22 May 2013
  • Nastaran Tower construction site, inspection photo 4, 22 May 2013

13 November 2012

58%

  • Nastaran Tower construction site, inspection photo 1, 13 November 2012
  • Nastaran Tower construction site, inspection photo 2, 13 November 2012
  • Nastaran Tower construction site, inspection photo 3, 13 November 2012
  • Nastaran Tower construction site, inspection photo 4, 13 November 2012

All 82 site photos, by inspection date

Context

Jaddaf Waterfront has 13 projects under construction, 32% built on average.

Own a unit in Nastaran Tower?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Nastaran Tower handover date?
Construction of Nastaran Tower is recorded as complete, with a registered completion date of November 2016. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Nastaran Tower?
Nastaran Tower was 100% built at the site inspection on 3 November 2016. The site has been inspected 6 times since November 2012. The Land Department took 82 site photos at its inspections.
Is Nastaran Tower delayed?
The register lists construction as complete.
Who is building Nastaran Tower?
The registered developer is Raam Limited.
Which bank holds the escrow account for Nastaran Tower?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.