Boutique Xll construction progress

The register lists Boutique Xll in Jaddaf Waterfront as complete, with a registered completion date of October 2023. Its last site inspection on record was in July 2024. The developer is Structure Real Estate Development.

100%

Built, at the site inspection of 22 July 2024

Construction complete

Registered completion date
October 2023
Construction started
March 2022
First registered
March 2022
Developer
Structure Real Estate Development
Units
129
Escrow bank
The National Bank of Fujairah
Name in Arabic
بوتيك Xll
Project number
2371
Site inspections
3

Schedule

The register lists Boutique Xll as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%20232024
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

22 July 2024

100%+86 pts

  • Boutique Xll construction site, inspection photo 1, 22 July 2024
  • Boutique Xll construction site, inspection photo 2, 22 July 2024
  • Boutique Xll construction site, inspection photo 3, 22 July 2024
  • Boutique Xll construction site, inspection photo 4, 22 July 2024

29 December 2023

14%

  • Boutique Xll construction site, inspection photo 1, 29 December 2023
  • Boutique Xll construction site, inspection photo 2, 29 December 2023
  • Boutique Xll construction site, inspection photo 3, 29 December 2023
  • Boutique Xll construction site, inspection photo 4, 29 December 2023

25 July 2023

41%

  • Boutique Xll construction site, inspection photo 1, 25 July 2023
  • Boutique Xll construction site, inspection photo 2, 25 July 2023
  • Boutique Xll construction site, inspection photo 3, 25 July 2023
  • Boutique Xll construction site, inspection photo 4, 25 July 2023

All 24 site photos, by inspection date

Context

Jaddaf Waterfront has 13 projects under construction, 32% built on average.

Own a unit in Boutique Xll?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Boutique Xll handover date?
Construction of Boutique Xll is recorded as complete, with a registered completion date of October 2023. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Boutique Xll?
Boutique Xll was 100% built at the site inspection on 22 July 2024. The site has been inspected 3 times since July 2023. The Land Department took 24 site photos at its inspections.
Is Boutique Xll delayed?
The register lists construction as complete.
Who is building Boutique Xll?
The registered developer is Structure Real Estate Development.
Which bank holds the escrow account for Boutique Xll?
The National Bank of Fujairah. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.