Indigo Spectrum1 construction progress
The register lists Indigo Spectrum1 in International City Phase 1 as complete, with a registered completion date of April 2015. Its last site inspection on record was in April 2016. The developer is Mars Properties Investment Limited.
100%
Built, at the site inspection of 12 April 2016
Construction complete
- Registered completion date
- April 2015
- Construction started
- April 2008
- First registered
- November 2008
- Developer
- Mars Properties Investment Limited
- Community
- International City Phase 1
- Units
- 100
- Escrow bank
- Mashreq Bank
- Name in Arabic
- الطيف النيلي 1
- Project number
- 162
- Site inspections
- 7
Schedule
The register lists Indigo Spectrum1 as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.
Site inspections
12 April 2016
100%+2.4 pts
15 December 2014
98%+15 pts
17 August 2014
82%+10 pts
12 May 2014
72%+21 pts
2 February 2014
51%+6.5 pts
6 November 2013
45%+13 pts
4 June 2013
31%
Context
International City Phase 1 has 3 projects under construction, 46% built on average.
Own a unit in Indigo Spectrum1?
The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.
Notify me when it launchesQuestions
- When is the Indigo Spectrum1 handover date?
- Construction of Indigo Spectrum1 is recorded as complete, with a registered completion date of April 2015. Handover of individual units follows on the developer's schedule, which the register does not show.
- What is the latest construction update on Indigo Spectrum1?
- Indigo Spectrum1 was 100% built at the site inspection on 12 April 2016. The site has been inspected 7 times since June 2013. The Land Department took 74 site photos at its inspections.
- Is Indigo Spectrum1 delayed?
- The register lists construction as complete.
- Who is building Indigo Spectrum1?
- The registered developer is Mars Properties Investment Limited.
- Which bank holds the escrow account for Indigo Spectrum1?
- Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Tomorrow Commercial TowerNearby in International City Phase 1. 70%, Due July 2026, passed.
- Lusin Residences By Ermax DevelopmentNearby in International City Phase 1. 35%, Due December 2026.
- Longford Residences By Devan Real Estate DevelopmentNearby in International City Phase 1. 33%, Due May 2028.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.