Indigo Spectrum 2 construction progress

The register lists Indigo Spectrum 2 in International City Phase 1 as complete, with a registered completion date of August 2017. Its last site inspection on record was in November 2017. The developer is Mars Properties Investment Limited.

100%

Built, at the site inspection of 14 November 2017

Construction complete

Registered completion date
August 2017
Construction started
November 2014
First registered
January 2016
Developer
Mars Properties Investment Limited
Units
91
Escrow bank
Mashreq Bank
Name in Arabic
الطيف النيلي 2
Project number
1241
Site inspections
8

Schedule

The register lists Indigo Spectrum 2 as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2014201520162017
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

14 November 2017

100%+19 pts

  • Indigo Spectrum 2 construction site, inspection photo 1, 14 November 2017
  • Indigo Spectrum 2 construction site, inspection photo 2, 14 November 2017
  • Indigo Spectrum 2 construction site, inspection photo 3, 14 November 2017
  • Indigo Spectrum 2 construction site, inspection photo 4, 14 November 2017

13 June 2017

81%+19 pts

  • Indigo Spectrum 2 construction site, inspection photo 1, 13 June 2017
  • Indigo Spectrum 2 construction site, inspection photo 2, 13 June 2017
  • Indigo Spectrum 2 construction site, inspection photo 3, 13 June 2017
  • Indigo Spectrum 2 construction site, inspection photo 4, 13 June 2017

13 March 2017

62%+11 pts

  • Indigo Spectrum 2 construction site, inspection photo 1, 13 March 2017
  • Indigo Spectrum 2 construction site, inspection photo 2, 13 March 2017
  • Indigo Spectrum 2 construction site, inspection photo 3, 13 March 2017
  • Indigo Spectrum 2 construction site, inspection photo 4, 13 March 2017

17 January 2017

51%+30 pts

  • Indigo Spectrum 2 construction site, inspection photo 1, 17 January 2017
  • Indigo Spectrum 2 construction site, inspection photo 2, 17 January 2017
  • Indigo Spectrum 2 construction site, inspection photo 3, 17 January 2017
  • Indigo Spectrum 2 construction site, inspection photo 4, 17 January 2017

27 July 2016

21%+16 pts

  • Indigo Spectrum 2 construction site, inspection photo 1, 27 July 2016
  • Indigo Spectrum 2 construction site, inspection photo 2, 27 July 2016
  • Indigo Spectrum 2 construction site, inspection photo 3, 27 July 2016
  • Indigo Spectrum 2 construction site, inspection photo 4, 27 July 2016

18 May 2015

5.0%+3.3 pts

  • Indigo Spectrum 2 construction site, inspection photo 1, 18 May 2015
  • Indigo Spectrum 2 construction site, inspection photo 2, 18 May 2015
  • Indigo Spectrum 2 construction site, inspection photo 3, 18 May 2015
  • Indigo Spectrum 2 construction site, inspection photo 4, 18 May 2015

9 December 2014

1.7%+1.7 pts

  • Indigo Spectrum 2 construction site, inspection photo 1, 9 December 2014
  • Indigo Spectrum 2 construction site, inspection photo 2, 9 December 2014
  • Indigo Spectrum 2 construction site, inspection photo 3, 9 December 2014
  • Indigo Spectrum 2 construction site, inspection photo 4, 9 December 2014

23 September 2013

0%

  • Indigo Spectrum 2 construction site, inspection photo 1, 23 September 2013

All 64 site photos, by inspection date

Context

International City Phase 1 has 3 projects under construction, 46% built on average.

Own a unit in Indigo Spectrum 2?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Indigo Spectrum 2 handover date?
Construction of Indigo Spectrum 2 is recorded as complete, with a registered completion date of August 2017. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Indigo Spectrum 2?
Indigo Spectrum 2 was 100% built at the site inspection on 14 November 2017. The site has been inspected 8 times since September 2013. The Land Department took 64 site photos at its inspections.
Is Indigo Spectrum 2 delayed?
The register lists construction as complete.
Who is building Indigo Spectrum 2?
The registered developer is Mars Properties Investment Limited.
Which bank holds the escrow account for Indigo Spectrum 2?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.