Indigo Optima 1 construction progress

The register lists Indigo Optima 1 in International City Phase 1 as complete, with a registered completion date of December 2014. Its last site inspection on record was in April 2016. The developer is Mars Properties Investment Limited.

100%

Built, at the site inspection of 12 April 2016

Construction complete

Registered completion date
December 2014
Construction started
March 2008
First registered
November 2008
Developer
Mars Properties Investment Limited
Units
144
Escrow bank
Mashreq Bank
Name in Arabic
نيلي أوبتيما 1
Project number
163
Site inspections
7

Schedule

The register lists Indigo Optima 1 as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2009201120132015
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

12 April 2016

100%+3.2 pts

  • Indigo Optima 1 construction site, inspection photo 1, 12 April 2016
  • Indigo Optima 1 construction site, inspection photo 2, 12 April 2016
  • Indigo Optima 1 construction site, inspection photo 3, 12 April 2016
  • Indigo Optima 1 construction site, inspection photo 4, 12 April 2016

10 February 2015

97%+22 pts

  • Indigo Optima 1 construction site, inspection photo 1, 10 February 2015
  • Indigo Optima 1 construction site, inspection photo 2, 10 February 2015
  • Indigo Optima 1 construction site, inspection photo 3, 10 February 2015
  • Indigo Optima 1 construction site, inspection photo 4, 10 February 2015

22 October 2014

75%+24 pts

  • Indigo Optima 1 construction site, inspection photo 1, 22 October 2014
  • Indigo Optima 1 construction site, inspection photo 2, 22 October 2014
  • Indigo Optima 1 construction site, inspection photo 3, 22 October 2014
  • Indigo Optima 1 construction site, inspection photo 4, 22 October 2014

15 July 2014

51%+13 pts

  • Indigo Optima 1 construction site, inspection photo 1, 15 July 2014
  • Indigo Optima 1 construction site, inspection photo 2, 15 July 2014
  • Indigo Optima 1 construction site, inspection photo 3, 15 July 2014
  • Indigo Optima 1 construction site, inspection photo 4, 15 July 2014

3 April 2014

38%+7.3 pts

  • Indigo Optima 1 construction site, inspection photo 1, 3 April 2014
  • Indigo Optima 1 construction site, inspection photo 2, 3 April 2014
  • Indigo Optima 1 construction site, inspection photo 3, 3 April 2014
  • Indigo Optima 1 construction site, inspection photo 4, 3 April 2014

11 February 2014

30%+8.3 pts

  • Indigo Optima 1 construction site, inspection photo 1, 11 February 2014
  • Indigo Optima 1 construction site, inspection photo 2, 11 February 2014
  • Indigo Optima 1 construction site, inspection photo 3, 11 February 2014
  • Indigo Optima 1 construction site, inspection photo 4, 11 February 2014

3 October 2013

22%

  • Indigo Optima 1 construction site, inspection photo 1, 3 October 2013
  • Indigo Optima 1 construction site, inspection photo 2, 3 October 2013
  • Indigo Optima 1 construction site, inspection photo 3, 3 October 2013
  • Indigo Optima 1 construction site, inspection photo 4, 3 October 2013

All 77 site photos, by inspection date

Context

International City Phase 1 has 3 projects under construction, 46% built on average.

Own a unit in Indigo Optima 1?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Indigo Optima 1 handover date?
Construction of Indigo Optima 1 is recorded as complete, with a registered completion date of December 2014. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Indigo Optima 1?
Indigo Optima 1 was 100% built at the site inspection on 12 April 2016. The site has been inspected 7 times since October 2013. The Land Department took 77 site photos at its inspections.
Is Indigo Optima 1 delayed?
The register lists construction as complete.
Who is building Indigo Optima 1?
The registered developer is Mars Properties Investment Limited.
Which bank holds the escrow account for Indigo Optima 1?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.