Mag Eye Phase 1 construction progress

The register lists Mag Eye Phase 1 in Hadaeq Sheikh Mohammed Bin Rashid - Disrict 7 as complete, with a registered completion date of August 2024. Its last site inspection on record was in August 2024. The developer is Mag Eye Real Estate Development.

100%

Built, at the site inspection of 16 August 2024

Construction complete

Registered completion date
August 2024
Construction started
May 2018
First registered
March 2018
Developer
Mag Eye Real Estate Development
Community
Hadaeq Sheikh Mohammed Bin Rashid - Disrict 7
Units
128
Escrow bank
Emirates NBD
Name in Arabic
ماج آي المرحلة 1
Project number
2033
Site inspections
16

Schedule

The register lists Mag Eye Phase 1 as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%201920212023
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

16 August 2024

100%+5.5 pts

  • Mag Eye Phase 1 construction site, inspection photo 1, 16 August 2024
  • Mag Eye Phase 1 construction site, inspection photo 2, 16 August 2024
  • Mag Eye Phase 1 construction site, inspection photo 3, 16 August 2024
  • Mag Eye Phase 1 construction site, inspection photo 4, 16 August 2024

3 July 2024

95%+0.5 pts

  • Mag Eye Phase 1 construction site, inspection photo 1, 3 July 2024
  • Mag Eye Phase 1 construction site, inspection photo 2, 3 July 2024
  • Mag Eye Phase 1 construction site, inspection photo 3, 3 July 2024
  • Mag Eye Phase 1 construction site, inspection photo 4, 3 July 2024

11 June 2024

94%+12 pts

  • Mag Eye Phase 1 construction site, inspection photo 1, 11 June 2024
  • Mag Eye Phase 1 construction site, inspection photo 2, 11 June 2024
  • Mag Eye Phase 1 construction site, inspection photo 3, 11 June 2024
  • Mag Eye Phase 1 construction site, inspection photo 4, 11 June 2024

12 June 2023

82%+8.7 pts

  • Mag Eye Phase 1 construction site, inspection photo 1, 12 June 2023
  • Mag Eye Phase 1 construction site, inspection photo 2, 12 June 2023
  • Mag Eye Phase 1 construction site, inspection photo 3, 12 June 2023
  • Mag Eye Phase 1 construction site, inspection photo 4, 12 June 2023

26 September 2022

73%+19 pts

  • Mag Eye Phase 1 construction site, inspection photo 1, 26 September 2022
  • Mag Eye Phase 1 construction site, inspection photo 2, 26 September 2022
  • Mag Eye Phase 1 construction site, inspection photo 3, 26 September 2022
  • Mag Eye Phase 1 construction site, inspection photo 4, 26 September 2022

11 April 2022

54%+13 pts

  • Mag Eye Phase 1 construction site, inspection photo 1, 11 April 2022
  • Mag Eye Phase 1 construction site, inspection photo 2, 11 April 2022
  • Mag Eye Phase 1 construction site, inspection photo 3, 11 April 2022
  • Mag Eye Phase 1 construction site, inspection photo 4, 11 April 2022

18 January 2022

41%+14 pts

  • Mag Eye Phase 1 construction site, inspection photo 1, 18 January 2022
  • Mag Eye Phase 1 construction site, inspection photo 2, 18 January 2022
  • Mag Eye Phase 1 construction site, inspection photo 3, 18 January 2022
  • Mag Eye Phase 1 construction site, inspection photo 4, 18 January 2022

12 September 2021

27%+7.1 pts

  • Mag Eye Phase 1 construction site, inspection photo 1, 12 September 2021
  • Mag Eye Phase 1 construction site, inspection photo 2, 12 September 2021
  • Mag Eye Phase 1 construction site, inspection photo 3, 12 September 2021
  • Mag Eye Phase 1 construction site, inspection photo 4, 12 September 2021

3 May 2021

20%+9.5 pts

  • Mag Eye Phase 1 construction site, inspection photo 1, 3 May 2021
  • Mag Eye Phase 1 construction site, inspection photo 2, 3 May 2021
  • Mag Eye Phase 1 construction site, inspection photo 3, 3 May 2021
  • Mag Eye Phase 1 construction site, inspection photo 4, 3 May 2021

2 February 2021

11%+5.0 pts

  • Mag Eye Phase 1 construction site, inspection photo 1, 2 February 2021
  • Mag Eye Phase 1 construction site, inspection photo 2, 2 February 2021
  • Mag Eye Phase 1 construction site, inspection photo 3, 2 February 2021
  • Mag Eye Phase 1 construction site, inspection photo 4, 2 February 2021

All 156 site photos, by inspection date

Context

Own a unit in Mag Eye Phase 1?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Mag Eye Phase 1 handover date?
Construction of Mag Eye Phase 1 is recorded as complete, with a registered completion date of August 2024. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Mag Eye Phase 1?
Mag Eye Phase 1 was 100% built at the site inspection on 16 August 2024. The site has been inspected 16 times since November 2018. The Land Department took 156 site photos at its inspections.
Is Mag Eye Phase 1 delayed?
The register lists construction as complete.
Who is building Mag Eye Phase 1?
The registered developer is Mag Eye Real Estate Development.
Which bank holds the escrow account for Mag Eye Phase 1?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.