Keturah Reserve construction progress

Keturah Reserve in Hadaeq Sheikh Mohammed Bin Rashid - Disrict 7 is 10% built at the Land Department inspection of August 2026. Developer Mag Park Real Estate Development. Completion registered for June 2027.

10%

Built, at the Land Department site inspection of 3 August 2026

Running behind its date

Completion date (Land Department)
June 2027
Finish at recent pace
November 2040
Construction started
December 2022
Registered with the Land Department
May 2024
Developer
Mag Park Real Estate Development
Community
Hadaeq Sheikh Mohammed Bin Rashid - Disrict 7
Units
281
Escrow bank
Emirates NBD
Name in Arabic
كيتوراه ريزيرف
Land Department project number
2924
Land Department site inspections
5

Schedule

Between November 2025 and August 2026 the site added about 0.5 points a month. At that rate it would finish around November 2040, more than three months after the June 2027 date registered with the Land Department.

0%25%50%75%100%20232024202520262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

3 August 2026

10%+2.8 pts

  • Keturah Reserve construction site, Land Department inspection photo 1, 3 August 2026
  • Keturah Reserve construction site, Land Department inspection photo 2, 3 August 2026
  • Keturah Reserve construction site, Land Department inspection photo 3, 3 August 2026
  • Keturah Reserve construction site, Land Department inspection photo 4, 3 August 2026

29 April 2026

7.3%+1.8 pts

  • Keturah Reserve construction site, Land Department inspection photo 1, 29 April 2026
  • Keturah Reserve construction site, Land Department inspection photo 2, 29 April 2026
  • Keturah Reserve construction site, Land Department inspection photo 3, 29 April 2026
  • Keturah Reserve construction site, Land Department inspection photo 4, 29 April 2026

10 November 2025

5.4%+3.9 pts

  • Keturah Reserve construction site, Land Department inspection photo 1, 10 November 2025
  • Keturah Reserve construction site, Land Department inspection photo 2, 10 November 2025
  • Keturah Reserve construction site, Land Department inspection photo 3, 10 November 2025
  • Keturah Reserve construction site, Land Department inspection photo 4, 10 November 2025

31 January 2025

1.5%+1.5 pts

  • Keturah Reserve construction site, Land Department inspection photo 1, 31 January 2025
  • Keturah Reserve construction site, Land Department inspection photo 2, 31 January 2025
  • Keturah Reserve construction site, Land Department inspection photo 3, 31 January 2025
  • Keturah Reserve construction site, Land Department inspection photo 4, 31 January 2025

14 February 2024

0%

  • Keturah Reserve construction site, Land Department inspection photo 1, 14 February 2024
  • Keturah Reserve construction site, Land Department inspection photo 2, 14 February 2024

All 28 site photos, by inspection date

Context

Own a unit in Keturah Reserve?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Keturah Reserve be completed?
The completion date registered with the Dubai Land Department is June 2027. At the pace of its recent inspections the site would reach 100% around November 2040. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Keturah Reserve is built?
10%, measured at the Land Department site inspection on 3 August 2026. The Land Department engineers have inspected the site 5 times since February 2024.
Is Keturah Reserve delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2027.
Who is building Keturah Reserve?
The registered developer is Mag Park Real Estate Development.
Which bank holds the escrow account for Keturah Reserve?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.