Skip to content

Keturah Reserve construction progress

The registered completion date for Keturah Reserve in Hadaeq Sheikh Mohammed Bin Rashid - Disrict 7 is June 2027. At the last site inspection, in August 2026, it was 10% built. The developer is Mag Park Real Estate Development.

10%

Built, at the site inspection of 3 August 2026

Running behind its date

Registered completion date
June 2027
Finish at recent pace
November 2040
Construction started
December 2022
First registered
May 2024
Developer
Mag Park Real Estate Development
Community
Hadaeq Sheikh Mohammed Bin Rashid - Disrict 7
Units
281
Escrow bank
Emirates NBD
Name in Arabic
كيتوراه ريزيرف
Project number
2924
Site inspections
5

Schedule

Between November 2025 and August 2026 the site added about 0.5 points a month. At that rate it would finish around November 2040, more than three months after its registered date of June 2027.

0%25%50%75%100%20232024202520262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

3 August 2026

10%+2.8 pts

  • Keturah Reserve construction site, inspection photo 1, 3 August 2026
  • Keturah Reserve construction site, inspection photo 2, 3 August 2026
  • Keturah Reserve construction site, inspection photo 3, 3 August 2026
  • Keturah Reserve construction site, inspection photo 4, 3 August 2026

29 April 2026

7.3%+1.8 pts

  • Keturah Reserve construction site, inspection photo 1, 29 April 2026
  • Keturah Reserve construction site, inspection photo 2, 29 April 2026
  • Keturah Reserve construction site, inspection photo 3, 29 April 2026
  • Keturah Reserve construction site, inspection photo 4, 29 April 2026

10 November 2025

5.4%+3.9 pts

  • Keturah Reserve construction site, inspection photo 1, 10 November 2025
  • Keturah Reserve construction site, inspection photo 2, 10 November 2025
  • Keturah Reserve construction site, inspection photo 3, 10 November 2025
  • Keturah Reserve construction site, inspection photo 4, 10 November 2025

31 January 2025

1.5%+1.5 pts

  • Keturah Reserve construction site, inspection photo 1, 31 January 2025
  • Keturah Reserve construction site, inspection photo 2, 31 January 2025
  • Keturah Reserve construction site, inspection photo 3, 31 January 2025
  • Keturah Reserve construction site, inspection photo 4, 31 January 2025

14 February 2024

0%

  • Keturah Reserve construction site, inspection photo 1, 14 February 2024
  • Keturah Reserve construction site, inspection photo 2, 14 February 2024

All 28 site photos, by inspection date

Context

Own a unit in Keturah Reserve?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Keturah Reserve handover date?
The registered completion date is June 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around November 2040. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Keturah Reserve?
Keturah Reserve was 10% built at the site inspection on 3 August 2026. The site has been inspected 5 times since February 2024. The Land Department took 28 site photos at its inspections.
Is Keturah Reserve delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2027.
Who is building Keturah Reserve?
The registered developer is Mag Park Real Estate Development.
Which bank holds the escrow account for Keturah Reserve?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.