Serra Residence By Wujod construction progress

The registered completion date for Serra Residence By Wujod is December 2027. At the last site inspection, in September 2026, it was 29% built. The developer is Wujod Real Estate Development.

29%

Built, at the site inspection of 30 September 2026

Running behind its date

Registered completion date
December 2027
Finish at recent pace
June 2028
Construction started
November 2025
First registered
March 2026
Developer
Wujod Real Estate Development
Units
20
Escrow bank
National Bank of Ras Al Khaimah
Name in Arabic
سيرا ريزدنس من وجود
Project number
4272
Site inspections
2

Schedule

Between January 2026 and September 2026 the site added about 3.4 points a month. At that rate it would finish around June 2028, more than three months after its registered date of December 2027.

0%25%50%75%100%20262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

30 September 2026

29%+29 pts

  • Serra Residence By Wujod construction site, inspection photo 1, 30 September 2026
  • Serra Residence By Wujod construction site, inspection photo 2, 30 September 2026
  • Serra Residence By Wujod construction site, inspection photo 3, 30 September 2026
  • Serra Residence By Wujod construction site, inspection photo 4, 30 September 2026

16 January 2026

0%

  • Serra Residence By Wujod construction site, inspection photo 1, 16 January 2026
  • Serra Residence By Wujod construction site, inspection photo 2, 16 January 2026
  • Serra Residence By Wujod construction site, inspection photo 3, 16 January 2026

All 12 site photos, by inspection date

Context

Own a unit in Serra Residence By Wujod?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Serra Residence By Wujod handover date?
The registered completion date is December 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around June 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Serra Residence By Wujod?
Serra Residence By Wujod was 29% built at the site inspection on 30 September 2026. The site has been inspected 2 times since January 2026. The Land Department took 12 site photos at its inspections.
Is Serra Residence By Wujod delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2027.
Who is building Serra Residence By Wujod?
The registered developer is Wujod Real Estate Development.
Which bank holds the escrow account for Serra Residence By Wujod?
National Bank of Ras Al Khaimah. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.