Oasis Tower 2 construction photos

152 photos from 15 site inspections, newest first. The percentage is how much of Oasis Tower 2 was built on the day of each visit.

8 September 202674% built

15 November 202274% built

1 August 202273% built

23 May 202273% built

2 March 202272% built

4 September 201872% built

1 April 201868% built

27 March 201758% built

6 October 201651% built

4 May 201643% built

17 January 201637% built

1 April 201531% built

8 June 201419% built

10 March 201415% built

6 October 201311% built

Back to Oasis Tower 2 construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.