Oasis Tower 2 construction progress
The registered completion date for Oasis Tower 2 is June 2027. At the last site inspection, in September 2026, it was 74% built. The developer is P A L Developments.
74%
Built, at the site inspection of 8 September 2026
Running behind its date
- Registered completion date
- June 2027
- Finish at recent pace
- July 2856
- Construction started
- September 2013
- First registered
- April 2026
- Developer
- P A L Developments
- Units
- 444
- Escrow bank
- Abu Dhabi Commercial Bank
- Name in Arabic
- أويسس تاور 2
- Project number
- 1560
- Site inspections
- 15
Schedule
Between November 2022 and September 2026 the site added about 0.0 points a month. At that rate it would finish around July 2856, more than three months after its registered date of June 2027.
Site inspections
8 September 2026
74%+0.1 pts
15 November 2022
74%+0.6 pts
1 August 2022
73%+0.4 pts
23 May 2022
73%+0.5 pts
2 March 2022
72%+0.0 pts
4 September 2018
72%+4.0 pts
1 April 2018
68%+10 pts
27 March 2017
58%+6.5 pts
6 October 2016
51%+8.7 pts
4 May 2016
43%+5.5 pts
Context
Own a unit in Oasis Tower 2?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Oasis Tower 2 handover date?
- The registered completion date is June 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around July 2856. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Oasis Tower 2?
- Oasis Tower 2 was 74% built at the site inspection on 8 September 2026. The site has been inspected 15 times since October 2013. The Land Department took 152 site photos at its inspections.
- Is Oasis Tower 2 delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2027.
- Who is building Oasis Tower 2?
- The registered developer is P A L Developments.
- Which bank holds the escrow account for Oasis Tower 2?
- Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.