Oasis Tower 2 construction progress

The registered completion date for Oasis Tower 2 is June 2027. At the last site inspection, in September 2026, it was 74% built. The developer is P A L Developments.

74%

Built, at the site inspection of 8 September 2026

Running behind its date

Registered completion date
June 2027
Finish at recent pace
July 2856
Construction started
September 2013
First registered
April 2026
Developer
P A L Developments
Units
444
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
أويسس تاور 2
Project number
1560
Site inspections
15

Schedule

Between November 2022 and September 2026 the site added about 0.0 points a month. At that rate it would finish around July 2856, more than three months after its registered date of June 2027.

0%25%50%75%100%20142017202020232026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

8 September 2026

74%+0.1 pts

  • Oasis Tower 2 construction site, inspection photo 1, 8 September 2026
  • Oasis Tower 2 construction site, inspection photo 2, 8 September 2026
  • Oasis Tower 2 construction site, inspection photo 3, 8 September 2026
  • Oasis Tower 2 construction site, inspection photo 4, 8 September 2026

15 November 2022

74%+0.6 pts

  • Oasis Tower 2 construction site, inspection photo 1, 15 November 2022
  • Oasis Tower 2 construction site, inspection photo 2, 15 November 2022
  • Oasis Tower 2 construction site, inspection photo 3, 15 November 2022
  • Oasis Tower 2 construction site, inspection photo 4, 15 November 2022

1 August 2022

73%+0.4 pts

  • Oasis Tower 2 construction site, inspection photo 1, 1 August 2022
  • Oasis Tower 2 construction site, inspection photo 2, 1 August 2022
  • Oasis Tower 2 construction site, inspection photo 3, 1 August 2022
  • Oasis Tower 2 construction site, inspection photo 4, 1 August 2022

23 May 2022

73%+0.5 pts

  • Oasis Tower 2 construction site, inspection photo 1, 23 May 2022
  • Oasis Tower 2 construction site, inspection photo 2, 23 May 2022
  • Oasis Tower 2 construction site, inspection photo 3, 23 May 2022
  • Oasis Tower 2 construction site, inspection photo 4, 23 May 2022

2 March 2022

72%+0.0 pts

  • Oasis Tower 2 construction site, inspection photo 1, 2 March 2022
  • Oasis Tower 2 construction site, inspection photo 2, 2 March 2022
  • Oasis Tower 2 construction site, inspection photo 3, 2 March 2022
  • Oasis Tower 2 construction site, inspection photo 4, 2 March 2022

4 September 2018

72%+4.0 pts

  • Oasis Tower 2 construction site, inspection photo 1, 4 September 2018
  • Oasis Tower 2 construction site, inspection photo 2, 4 September 2018
  • Oasis Tower 2 construction site, inspection photo 3, 4 September 2018
  • Oasis Tower 2 construction site, inspection photo 4, 4 September 2018

1 April 2018

68%+10 pts

  • Oasis Tower 2 construction site, inspection photo 1, 1 April 2018
  • Oasis Tower 2 construction site, inspection photo 2, 1 April 2018
  • Oasis Tower 2 construction site, inspection photo 3, 1 April 2018
  • Oasis Tower 2 construction site, inspection photo 4, 1 April 2018

27 March 2017

58%+6.5 pts

  • Oasis Tower 2 construction site, inspection photo 1, 27 March 2017
  • Oasis Tower 2 construction site, inspection photo 2, 27 March 2017
  • Oasis Tower 2 construction site, inspection photo 3, 27 March 2017
  • Oasis Tower 2 construction site, inspection photo 4, 27 March 2017

6 October 2016

51%+8.7 pts

  • Oasis Tower 2 construction site, inspection photo 1, 6 October 2016
  • Oasis Tower 2 construction site, inspection photo 2, 6 October 2016
  • Oasis Tower 2 construction site, inspection photo 3, 6 October 2016
  • Oasis Tower 2 construction site, inspection photo 4, 6 October 2016

4 May 2016

43%+5.5 pts

  • Oasis Tower 2 construction site, inspection photo 1, 4 May 2016
  • Oasis Tower 2 construction site, inspection photo 2, 4 May 2016
  • Oasis Tower 2 construction site, inspection photo 3, 4 May 2016
  • Oasis Tower 2 construction site, inspection photo 4, 4 May 2016

All 152 site photos, by inspection date

Context

Own a unit in Oasis Tower 2?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Oasis Tower 2 handover date?
The registered completion date is June 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around July 2856. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Oasis Tower 2?
Oasis Tower 2 was 74% built at the site inspection on 8 September 2026. The site has been inspected 15 times since October 2013. The Land Department took 152 site photos at its inspections.
Is Oasis Tower 2 delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2027.
Who is building Oasis Tower 2?
The registered developer is P A L Developments.
Which bank holds the escrow account for Oasis Tower 2?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.