Al Ezz Tower By Abualnaga construction progress

The registered completion date for Al Ezz Tower By Abualnaga is December 2029. At the last site inspection, in November 2026, it was 3.2% built. The developer is Abualnaga Development.

3.2%

Built, at the site inspection of 3 November 2026

Running behind its date

Registered completion date
December 2029
Finish at recent pace
August 2035
Construction started
July 2026
First registered
November 2026
Developer
Abualnaga Development
Units
202
Escrow bank
Emirates NBD
Name in Arabic
العز تاور من ابو النجا
Project number
4492
Site inspections
2

Schedule

Between September 2026 and November 2026 the site added about 0.9 points a month. At that rate it would finish around August 2035, more than three months after its registered date of December 2029.

0%25%50%75%100%202720282029
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

3 November 2026

3.2%+1.5 pts

  • Al Ezz Tower By Abualnaga construction site, inspection photo 1, 3 November 2026
  • Al Ezz Tower By Abualnaga construction site, inspection photo 2, 3 November 2026
  • Al Ezz Tower By Abualnaga construction site, inspection photo 3, 3 November 2026
  • Al Ezz Tower By Abualnaga construction site, inspection photo 4, 3 November 2026

14 September 2026

1.7%

  • Al Ezz Tower By Abualnaga construction site, inspection photo 1, 14 September 2026
  • Al Ezz Tower By Abualnaga construction site, inspection photo 2, 14 September 2026

All 6 site photos, by inspection date

Context

Abualnaga Development has 2 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Al Ezz Tower By Abualnaga?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Al Ezz Tower By Abualnaga handover date?
The registered completion date is December 2029. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around August 2035. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Al Ezz Tower By Abualnaga?
Al Ezz Tower By Abualnaga was 3.2% built at the site inspection on 3 November 2026. The site has been inspected 2 times since September 2026. The Land Department took 6 site photos at its inspections.
Is Al Ezz Tower By Abualnaga delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2029.
Who is building Al Ezz Tower By Abualnaga?
The registered developer is Abualnaga Development. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Al Ezz Tower By Abualnaga?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.