Greenway construction photos

41 photos taken by Dubai Land Department engineers at 8 site inspections, newest first. The percentage is how much of Greenway was built on the day of each visit.

20 July 202639% built

17 March 202632% built

12 December 202523% built

19 September 202515% built

25 June 20257.0% built

7 March 20250.2% built

4 November 20240% built

1 April 20240% built

Back to Greenway construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.