Fairway Residences By Prescott construction photos
55 photos from 8 site inspections, newest first. The percentage is how much of Fairway Residences By Prescott was built on the day of each visit.
30 September 202650% built
23 June 202643% built
18 March 202633% built
18 December 202521% built
17 October 202516% built
19 May 20257.4% built
28 January 20251.5% built
15 May 20240% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.