Signature Lifestyle Residences construction photos
15 photos from 4 site inspections, newest first. The percentage is how much of Signature Lifestyle Residences was built on the day of each visit.
24 August 20268.1% built
15 April 20266.3% built
10 July 20250.9% built
23 September 20240% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.