Mercer House construction progress

Mercer House in Dmcc-ez1 is 18% built at the Land Department inspection of August 2026. Developer Eln Properties Development. Completion registered for July 2027.

18%

Built, at the Land Department site inspection of 7 August 2026

Running behind its date

Completion date (Land Department)
July 2027
Finish at recent pace
November 2031
Construction started
March 2024
Registered with the Land Department
June 2024
Developer
Eln Properties Development
Community
Dmcc-ez1
Units
610
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
ميرسر هاوس
Land Department project number
2990
Land Department site inspections
5

Schedule

Between November 2025 and August 2026 the site added about 1.3 points a month. At that rate it would finish around November 2031, more than three months after the July 2027 date registered with the Land Department.

0%25%50%75%100%202520262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

7 August 2026

18%+4.2 pts

  • Mercer House construction site, Land Department inspection photo 1, 7 August 2026
  • Mercer House construction site, Land Department inspection photo 2, 7 August 2026
  • Mercer House construction site, Land Department inspection photo 3, 7 August 2026
  • Mercer House construction site, Land Department inspection photo 4, 7 August 2026

2 April 2026

14%+6.8 pts

  • Mercer House construction site, Land Department inspection photo 1, 2 April 2026
  • Mercer House construction site, Land Department inspection photo 2, 2 April 2026
  • Mercer House construction site, Land Department inspection photo 3, 2 April 2026
  • Mercer House construction site, Land Department inspection photo 4, 2 April 2026

19 November 2025

7.1%+1.2 pts

  • Mercer House construction site, Land Department inspection photo 1, 19 November 2025
  • Mercer House construction site, Land Department inspection photo 2, 19 November 2025
  • Mercer House construction site, Land Department inspection photo 3, 19 November 2025
  • Mercer House construction site, Land Department inspection photo 4, 19 November 2025

4 June 2025

5.8%+5.8 pts

  • Mercer House construction site, Land Department inspection photo 1, 4 June 2025
  • Mercer House construction site, Land Department inspection photo 2, 4 June 2025
  • Mercer House construction site, Land Department inspection photo 3, 4 June 2025
  • Mercer House construction site, Land Department inspection photo 4, 4 June 2025

7 March 2024

0%

  • Mercer House construction site, Land Department inspection photo 1, 7 March 2024
  • Mercer House construction site, Land Department inspection photo 2, 7 March 2024
  • Mercer House construction site, Land Department inspection photo 3, 7 March 2024

All 28 site photos, by inspection date

Context

Dmcc-ez1 has 2 projects under construction, 13% built on average. Mercer House is ahead of that average.

Own a unit in Mercer House?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Track the handover

Questions

When will Mercer House be completed?
The completion date registered with the Dubai Land Department is July 2027. At the pace of its recent inspections the site would reach 100% around November 2031. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Mercer House is built?
18%, measured at the Land Department site inspection on 7 August 2026. The Land Department engineers have inspected the site 5 times since March 2024.
Is Mercer House delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of July 2027.
Who is building Mercer House?
The registered developer is Eln Properties Development.
Which bank holds the escrow account for Mercer House?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.