Damac Hills - Golf Promenade construction progress
The register lists Damac Hills - Golf Promenade in Damac Hills as complete, with a registered completion date of September 2019. Its last site inspection on record was in October 2019. The developer is Damac Crescent Properties.
100%
Built, at the site inspection of 3 October 2019
Construction complete
- Registered completion date
- September 2019
- Construction started
- August 2014
- First registered
- April 2014
- Developer
- Damac Crescent Properties
- Community
- Damac Hills
- Units
- 741
- Escrow bank
- Abu Dhabi Commercial Bank
- Name in Arabic
- دماك هيلز - جولف برومندي
- Project number
- 1504
- Site inspections
- 14
Schedule
The register lists Damac Hills - Golf Promenade as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.
Site inspections
3 October 2019
100%+2.7 pts
11 June 2019
97%+0.5 pts
28 November 2018
97%+1.7 pts
17 July 2018
95%+0.7 pts
18 March 2018
94%+3.7 pts
15 November 2017
91%+3.7 pts
10 July 2017
87%+25 pts
19 February 2017
62%+2.9 pts
7 December 2016
60%+9.4 pts
29 June 2016
50%+13 pts
Context
Damac Hills has 8 projects under construction, 38% built on average.
Damac Crescent Properties has 9 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in Damac Hills - Golf Promenade?
The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.
Notify me when it launchesQuestions
- When is the Damac Hills - Golf Promenade handover date?
- Construction of Damac Hills - Golf Promenade is recorded as complete, with a registered completion date of September 2019. Handover of individual units follows on the developer's schedule, which the register does not show.
- What is the latest construction update on Damac Hills - Golf Promenade?
- Damac Hills - Golf Promenade was 100% built at the site inspection on 3 October 2019. The site has been inspected 14 times since December 2014. The Land Department took 127 site photos at its inspections.
- Is Damac Hills - Golf Promenade delayed?
- The register lists construction as complete.
- Who is building Damac Hills - Golf Promenade?
- The registered developer is Damac Crescent Properties. It has 9 other projects under construction in Dubai.
- Which bank holds the escrow account for Damac Hills - Golf Promenade?
- Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Damac Hills - Gems Estates 1Also by Damac Crescent Properties. 49%, Due November 2026.
- Damac Hills - Gems Estates 2Also by Damac Crescent Properties. 63%, Due September 2024, passed.
- Damac Hills - Golf Gate 2Also by Damac Crescent Properties. 80%.
- Damac Hills - Golf Greens 1Also by Damac Crescent Properties. 41%, Due March 2027.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.