Damac District construction progress

Damac District in Damac Hills is 4.1% built at the Land Department inspection of September 2026. Developer Damac Crescent Properties. Completion registered for March 2029.

4.1%

Built, at the Land Department site inspection of 22 September 2026

Running behind its date

Completion date (Land Department)
March 2029
Finish at recent pace
February 2040
Construction started
February 2026
Registered with the Land Department
September 2025
Community
Damac Hills
Units
1,139
Escrow bank
Mashreq Bank
Name in Arabic
داماك ديستريكت
Land Department project number
4064
Land Department site inspections
3

Schedule

Between March 2026 and September 2026 the site added about 0.6 points a month. At that rate it would finish around February 2040, more than three months after the March 2029 date registered with the Land Department.

0%25%50%75%100%2026202720282029
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

22 September 2026

4.1%+4.0 pts

  • Damac District construction site, Land Department inspection photo 1, 22 September 2026
  • Damac District construction site, Land Department inspection photo 2, 22 September 2026
  • Damac District construction site, Land Department inspection photo 3, 22 September 2026
  • Damac District construction site, Land Department inspection photo 4, 22 September 2026

4 March 2026

0.1%+0.1 pts

  • Damac District construction site, Land Department inspection photo 1, 4 March 2026
  • Damac District construction site, Land Department inspection photo 2, 4 March 2026
  • Damac District construction site, Land Department inspection photo 3, 4 March 2026
  • Damac District construction site, Land Department inspection photo 4, 4 March 2026

28 August 2025

0%

  • Damac District construction site, Land Department inspection photo 1, 28 August 2025
  • Damac District construction site, Land Department inspection photo 2, 28 August 2025

All 12 site photos, by inspection date

Context

Damac Hills has 8 projects under construction, 36% built on average.

Damac Crescent Properties has 9 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Damac District?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Damac District be completed?
The completion date registered with the Dubai Land Department is March 2029. At the pace of its recent inspections the site would reach 100% around February 2040. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Damac District is built?
4.1%, measured at the Land Department site inspection on 22 September 2026. The Land Department engineers have inspected the site 3 times since August 2025.
Is Damac District delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2029.
Who is building Damac District?
The registered developer is Damac Crescent Properties. It has 8 other projects under construction in Dubai.
Which bank holds the escrow account for Damac District?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.