Damac District construction progress

The registered completion date for Damac District in Damac Hills is March 2029. At the last site inspection, in September 2026, it was 4.1% built. The developer is Damac Crescent Properties.

4.1%

Built, at the site inspection of 22 September 2026

Running behind its date

Registered completion date
March 2029
Finish at recent pace
February 2040
Construction started
February 2026
First registered
September 2025
Community
Damac Hills
Units
1,139
Escrow bank
Mashreq Bank
Name in Arabic
داماك ديستريكت
Project number
4064
Site inspections
3

Schedule

Between March 2026 and September 2026 the site added about 0.6 points a month. At that rate it would finish around February 2040, more than three months after its registered date of March 2029.

0%25%50%75%100%2026202720282029
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

22 September 2026

4.1%+4.0 pts

  • Damac District construction site, inspection photo 1, 22 September 2026
  • Damac District construction site, inspection photo 2, 22 September 2026
  • Damac District construction site, inspection photo 3, 22 September 2026
  • Damac District construction site, inspection photo 4, 22 September 2026

4 March 2026

0.1%+0.1 pts

  • Damac District construction site, inspection photo 1, 4 March 2026
  • Damac District construction site, inspection photo 2, 4 March 2026
  • Damac District construction site, inspection photo 3, 4 March 2026
  • Damac District construction site, inspection photo 4, 4 March 2026

28 August 2025

0%

  • Damac District construction site, inspection photo 1, 28 August 2025
  • Damac District construction site, inspection photo 2, 28 August 2025

All 12 site photos, by inspection date

Context

Damac Hills has 8 projects under construction, 38% built on average.

Damac Crescent Properties has 9 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Damac District?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Damac District handover date?
The registered completion date is March 2029. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around February 2040. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Damac District?
Damac District was 4.1% built at the site inspection on 22 September 2026. The site has been inspected 3 times since August 2025. The Land Department took 12 site photos at its inspections.
Is Damac District delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2029.
Who is building Damac District?
The registered developer is Damac Crescent Properties. It has 8 other projects under construction in Dubai.
Which bank holds the escrow account for Damac District?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.