Mohammed Bin Rashid Al Maktoum City-District One Phase II Villas construction progress
The register lists Mohammed Bin Rashid Al Maktoum City-District One Phase II Villas in Al Merkadh as complete, with a registered completion date of March 2020. Its last site inspection on record was in September 2020. The developer is District One.
100%
Built, at the site inspection of 24 September 2020
Construction complete
- Registered completion date
- March 2020
- Construction started
- February 2014
- First registered
- March 2014
- Developer
- District One
- Community
- Al Merkadh
- Units
- 241
- Escrow bank
- Dubai Islamic Bank
- Name in Arabic
- محمد بن راشد ال مكتوم ستي ديسترك ون فيس 2 فلل
- Project number
- 1496
- Site inspections
- 17
Schedule
The register lists Mohammed Bin Rashid Al Maktoum City-District One Phase II Villas as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.
Site inspections
24 September 2020
100%+1.5 pts
13 April 2020
99%+3.5 pts
20 October 2019
95%+4.9 pts
11 March 2019
90%+8.0 pts
11 October 2018
82%+17 pts
6 June 2018
66%+5.5 pts
13 February 2018
60%+9.9 pts
8 November 2017
50%+9.1 pts
19 July 2017
41%+11 pts
6 April 2017
30%+10 pts
Context
District One has 1 project under construction in Dubai, none past their registered completion dates.
Own a unit in Mohammed Bin Rashid Al Maktoum City-District One Phase II Villas?
The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.
Notify me when it launchesQuestions
- When is the Mohammed Bin Rashid Al Maktoum City-District One Phase II Villas handover date?
- Construction of Mohammed Bin Rashid Al Maktoum City-District One Phase II Villas is recorded as complete, with a registered completion date of March 2020. Handover of individual units follows on the developer's schedule, which the register does not show.
- What is the latest construction update on Mohammed Bin Rashid Al Maktoum City-District One Phase II Villas?
- Mohammed Bin Rashid Al Maktoum City-District One Phase II Villas was 100% built at the site inspection on 24 September 2020. The site has been inspected 17 times since February 2015. The Land Department took 113 site photos at its inspections.
- Is Mohammed Bin Rashid Al Maktoum City-District One Phase II Villas delayed?
- The register lists construction as complete.
- Who is building Mohammed Bin Rashid Al Maktoum City-District One Phase II Villas?
- The registered developer is District One. It has 1 other project under construction in Dubai.
- Which bank holds the escrow account for Mohammed Bin Rashid Al Maktoum City-District One Phase II Villas?
- Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Naya At District OneAlso by District One. 68%, Due September 2027.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.