Mohammed Bin Rashid Al Maktoum City-District One Phase II Villas construction progress

The register lists Mohammed Bin Rashid Al Maktoum City-District One Phase II Villas in Al Merkadh as complete, with a registered completion date of March 2020. Its last site inspection on record was in September 2020. The developer is District One.

100%

Built, at the site inspection of 24 September 2020

Construction complete

Registered completion date
March 2020
Construction started
February 2014
First registered
March 2014
Developer
District One
Community
Al Merkadh
Units
241
Escrow bank
Dubai Islamic Bank
Name in Arabic
محمد بن راشد ال مكتوم ستي ديسترك ون فيس 2 فلل
Project number
1496
Site inspections
17

Schedule

The register lists Mohammed Bin Rashid Al Maktoum City-District One Phase II Villas as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%201520172019
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

24 September 2020

100%+1.5 pts

  • Mohammed Bin Rashid Al Maktoum City-District One Phase II Villas construction site, inspection photo 1, 24 September 2020
  • Mohammed Bin Rashid Al Maktoum City-District One Phase II Villas construction site, inspection photo 2, 24 September 2020
  • Mohammed Bin Rashid Al Maktoum City-District One Phase II Villas construction site, inspection photo 3, 24 September 2020
  • Mohammed Bin Rashid Al Maktoum City-District One Phase II Villas construction site, inspection photo 4, 24 September 2020

13 April 2020

99%+3.5 pts

  • Mohammed Bin Rashid Al Maktoum City-District One Phase II Villas construction site, inspection photo 1, 13 April 2020
  • Mohammed Bin Rashid Al Maktoum City-District One Phase II Villas construction site, inspection photo 2, 13 April 2020
  • Mohammed Bin Rashid Al Maktoum City-District One Phase II Villas construction site, inspection photo 3, 13 April 2020
  • Mohammed Bin Rashid Al Maktoum City-District One Phase II Villas construction site, inspection photo 4, 13 April 2020

20 October 2019

95%+4.9 pts

  • Mohammed Bin Rashid Al Maktoum City-District One Phase II Villas construction site, inspection photo 1, 20 October 2019
  • Mohammed Bin Rashid Al Maktoum City-District One Phase II Villas construction site, inspection photo 2, 20 October 2019
  • Mohammed Bin Rashid Al Maktoum City-District One Phase II Villas construction site, inspection photo 3, 20 October 2019
  • Mohammed Bin Rashid Al Maktoum City-District One Phase II Villas construction site, inspection photo 4, 20 October 2019

11 March 2019

90%+8.0 pts

  • Mohammed Bin Rashid Al Maktoum City-District One Phase II Villas construction site, inspection photo 1, 11 March 2019
  • Mohammed Bin Rashid Al Maktoum City-District One Phase II Villas construction site, inspection photo 2, 11 March 2019
  • Mohammed Bin Rashid Al Maktoum City-District One Phase II Villas construction site, inspection photo 3, 11 March 2019
  • Mohammed Bin Rashid Al Maktoum City-District One Phase II Villas construction site, inspection photo 4, 11 March 2019

11 October 2018

82%+17 pts

  • Mohammed Bin Rashid Al Maktoum City-District One Phase II Villas construction site, inspection photo 1, 11 October 2018
  • Mohammed Bin Rashid Al Maktoum City-District One Phase II Villas construction site, inspection photo 2, 11 October 2018
  • Mohammed Bin Rashid Al Maktoum City-District One Phase II Villas construction site, inspection photo 3, 11 October 2018
  • Mohammed Bin Rashid Al Maktoum City-District One Phase II Villas construction site, inspection photo 4, 11 October 2018

6 June 2018

66%+5.5 pts

  • Mohammed Bin Rashid Al Maktoum City-District One Phase II Villas construction site, inspection photo 1, 6 June 2018
  • Mohammed Bin Rashid Al Maktoum City-District One Phase II Villas construction site, inspection photo 2, 6 June 2018
  • Mohammed Bin Rashid Al Maktoum City-District One Phase II Villas construction site, inspection photo 3, 6 June 2018
  • Mohammed Bin Rashid Al Maktoum City-District One Phase II Villas construction site, inspection photo 4, 6 June 2018

13 February 2018

60%+9.9 pts

  • Mohammed Bin Rashid Al Maktoum City-District One Phase II Villas construction site, inspection photo 1, 13 February 2018
  • Mohammed Bin Rashid Al Maktoum City-District One Phase II Villas construction site, inspection photo 2, 13 February 2018
  • Mohammed Bin Rashid Al Maktoum City-District One Phase II Villas construction site, inspection photo 3, 13 February 2018
  • Mohammed Bin Rashid Al Maktoum City-District One Phase II Villas construction site, inspection photo 4, 13 February 2018

8 November 2017

50%+9.1 pts

  • Mohammed Bin Rashid Al Maktoum City-District One Phase II Villas construction site, inspection photo 1, 8 November 2017
  • Mohammed Bin Rashid Al Maktoum City-District One Phase II Villas construction site, inspection photo 2, 8 November 2017
  • Mohammed Bin Rashid Al Maktoum City-District One Phase II Villas construction site, inspection photo 3, 8 November 2017
  • Mohammed Bin Rashid Al Maktoum City-District One Phase II Villas construction site, inspection photo 4, 8 November 2017

19 July 2017

41%+11 pts

  • Mohammed Bin Rashid Al Maktoum City-District One Phase II Villas construction site, inspection photo 1, 19 July 2017
  • Mohammed Bin Rashid Al Maktoum City-District One Phase II Villas construction site, inspection photo 2, 19 July 2017
  • Mohammed Bin Rashid Al Maktoum City-District One Phase II Villas construction site, inspection photo 3, 19 July 2017
  • Mohammed Bin Rashid Al Maktoum City-District One Phase II Villas construction site, inspection photo 4, 19 July 2017

6 April 2017

30%+10 pts

  • Mohammed Bin Rashid Al Maktoum City-District One Phase II Villas construction site, inspection photo 1, 6 April 2017
  • Mohammed Bin Rashid Al Maktoum City-District One Phase II Villas construction site, inspection photo 2, 6 April 2017
  • Mohammed Bin Rashid Al Maktoum City-District One Phase II Villas construction site, inspection photo 3, 6 April 2017
  • Mohammed Bin Rashid Al Maktoum City-District One Phase II Villas construction site, inspection photo 4, 6 April 2017

All 113 site photos, by inspection date

Context

District One has 1 project under construction in Dubai, none past their registered completion dates.

Own a unit in Mohammed Bin Rashid Al Maktoum City-District One Phase II Villas?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Mohammed Bin Rashid Al Maktoum City-District One Phase II Villas handover date?
Construction of Mohammed Bin Rashid Al Maktoum City-District One Phase II Villas is recorded as complete, with a registered completion date of March 2020. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Mohammed Bin Rashid Al Maktoum City-District One Phase II Villas?
Mohammed Bin Rashid Al Maktoum City-District One Phase II Villas was 100% built at the site inspection on 24 September 2020. The site has been inspected 17 times since February 2015. The Land Department took 113 site photos at its inspections.
Is Mohammed Bin Rashid Al Maktoum City-District One Phase II Villas delayed?
The register lists construction as complete.
Who is building Mohammed Bin Rashid Al Maktoum City-District One Phase II Villas?
The registered developer is District One. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Mohammed Bin Rashid Al Maktoum City-District One Phase II Villas?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.