Downtown Views II construction photos

166 photos from 19 site inspections, newest first. The percentage is how much of Downtown Views II was built on the day of each visit.

30 December 2022100% built

31 August 202295% built

9 May 202292% built

9 December 202187% built

22 August 202183% built

17 May 202180% built

14 January 202168% built

28 September 202057% built

10 June 202042% built

18 February 202031% built

3 November 201923% built

21 July 201913% built

3 April 201911% built

22 January 20198.2% built

8 October 20185.8% built

28 June 20183.8% built

21 March 20182.8% built

12 December 20170.2% built

27 July 20170.1% built

Back to Downtown Views II construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.