Petalz By Danube construction photos

70 photos from 10 site inspections, newest first. The percentage is how much of Petalz By Danube was built on the day of each visit.

28 October 2025100% built

7 October 202599% built

24 September 202595% built

31 May 202578% built

9 January 202541% built

22 July 202411% built

20 March 20246.2% built

7 November 20231.7% built

5 June 20230% built

24 October 20220% built

Back to Petalz By Danube construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.