112 photos from 12 site inspections, newest first. The percentage is how much of Olivz Residence was built on the day of each visit.

13 May 2024100% built

29 November 202387% built

24 August 202361% built

21 June 202351% built

11 April 202340% built

21 December 202222% built

6 September 20229.2% built

10 May 20224.9% built

6 January 20222.8% built

22 September 20212.5% built

6 May 20211.4% built

1 February 20210.3% built

Back to Olivz Residence construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.