Aseel construction photos

79 photos from 8 site inspections, newest first. The percentage is how much of Aseel was built on the day of each visit.

31 October 2018100% built

20 March 201895% built

6 December 201783% built

8 August 201767% built

21 May 201756% built

16 February 201746% built

5 October 201620% built

5 March 20159.1% built

Back to Aseel construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.