Villanova Amaranta B construction photos

79 photos from 8 site inspections, newest first. The percentage is how much of Villanova Amaranta B was built on the day of each visit.

19 September 2021100% built

23 February 202196% built

29 June 202087% built

16 March 202071% built

25 December 201958% built

8 July 201930% built

26 March 201918% built

28 November 20187.4% built

Back to Villanova Amaranta B construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.