La Violeta 1 construction photos

43 photos from 6 site inspections, newest first. The percentage is how much of La Violeta 1 was built on the day of each visit.

11 November 2024100% built

9 May 202473% built

18 October 202340% built

24 July 202318% built

15 March 20234.5% built

13 October 20220.4% built

Back to La Violeta 1 construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.