97 photos from 10 site inspections, newest first. The percentage is how much of Arabian Ranches Lll - Ruba was built on the day of each visit.

19 February 2024100% built

4 July 202391% built

9 March 202382% built

28 November 202273% built

11 August 202261% built

21 April 202248% built

6 January 202234% built

30 September 202121% built

8 July 20217.3% built

15 March 20210.5% built

Back to Arabian Ranches Lll - Ruba construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.