Arabian Ranches Lll - June construction photos

84 photos from 10 site inspections, newest first. The percentage is how much of Arabian Ranches Lll - June was built on the day of each visit.

2 July 2025100% built

11 February 202587% built

30 September 202477% built

9 May 202461% built

14 November 202335% built

5 July 202313% built

9 March 20236.1% built

24 November 20222.2% built

11 August 20221.4% built

21 April 20220.4% built

Back to Arabian Ranches Lll - June construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.