Arabian Ranches Lll - Bliss 2 construction photos

71 photos from 10 site inspections, newest first. The percentage is how much of Arabian Ranches Lll - Bliss 2 was built on the day of each visit.

17 December 2025100% built

16 September 202594% built

30 June 202588% built

26 February 202580% built

10 October 202467% built

27 March 202437% built

7 August 202312% built

12 April 20233.3% built

13 December 20220.6% built

29 August 20220.1% built

Back to Arabian Ranches Lll - Bliss 2 construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.